Installation instructions for professionals
Half-warm space* can mean a lowered ceiling,
midsole, or casing.
NOTE
The duct coils to be installed in the ventilation
system must be insulated in the same way as the
ventilation ducts are. The ceiling mounting plate is
an extra sold separately.
NOTE
Outside air intake duct
(fresh air intake duct)
Cold space:
•
100 mm plate, mat or pipe insulation (+ additional
possible blowing wool).
Warm/semi-warm* space and suspended ceilings,
intermediate floor and enclosures:
•
Option 1: 80 mm insulation with steam-tight surface
•
Option 2: 20 mm cellular rubber insulation on the
surface of the duct and 50 mm insulation on the
steam-tight surface.
Insulation must prevent the condensation of steam on the
outer surface of the duct. In summer it must prevent the
air from heating too much.
Supply air duct
Cold/semi-warm* space and lowered ceilings,
intermediate floor and enclosures:
•
In basic ventilation, the insulation must be planned
and implemented so that changes in the temperature
of airflow are less than 1°C. It is possible to use 100
mm plate, mat or pipe insulation, for example (as well
as possible blowing wool).
Warm space:
•
Basic ventilation does not require insulation.
For heating and cooling uses, cf. tables “Insulating
ventilation ducts for heating” and “Insulating ventilation
ducts for cooling”.
Examples of ventilation duct insulation
Soundproofing is not included in these insulation
instructions and examples.
Exhaust air duct
Warm space:
•
Basic ventilation does not require insulation.
Cold/semi-warm* space:
•
In basic ventilation, the insulation must be planned
and implemented so that changes in the temperature
of airflow are less than 1°C. It is possible to use 100
mm plate, mat or pipe insulation, for example (as well
as possible blowing wool).
If used for heating or cooling, cf. tables “Insulating
ventilation ducts for heating” and “Insulating ventilation
ducts for cooling”.
Extract air duct
Cold space:
•
100 mm plate, mat or pipe insulation
Warm/semi-warm* space:
•
Option 1: 80 mm insulation with steam-tight surface
•
Option 2: 20 mm cellular rubber insulation on the
surface of the duct and 50 mm insulation on the
steam-tight surface.
Insulation must prevent the condensation of steam on the
inner and outer surface.
* semi-warm space = +5... +15°C
Summary of Contents for Pingvin XL eAir
Page 20: ...20 9 13 15 11 10 14 Lis varuste 1 2 min 12...
Page 46: ...46...
Page 48: ...48 2016 1254 2014 A A ENERGIA ENERGIJA ENERGY ENERGIE ENERGI PINGVIN XL A 47 dB 340 m3 h...
Page 49: ...49 Installationsanvisningar f r yrkesfolk...
Page 50: ...50 Pingvin XL eAir Installationsanvisningar f r ventilationsaggregat Svenska...
Page 68: ...68 9 13 15 11 10 14 Extra tillbeh r 1 2 min 12...
Page 94: ...94...
Page 96: ...96 2016 1254 2014 A A ENERGIA ENERGIJA ENERGY ENERGIE ENERGI PINGVIN XL A 47 dB 340 m3 h...
Page 97: ...97 Installasjonsinstrukser for fagfolk...
Page 98: ...98 Installeringsinstruksjoner for ventilasjonsenheten Norsk Pingvin XL eAir...
Page 116: ...116 9 13 15 11 10 14 Ekstrautstyr 1 2 min 12...
Page 142: ...142...
Page 144: ...144 2016 1254 2014 A A ENERGIA ENERGIJA ENERGY ENERGIE ENERGI PINGVIN XL A 47 dB 340 m3 h...
Page 145: ...145 Installation instructions for professionals...
Page 146: ...146 Pingvin XL eAir Installation instructions for the ventilation unit English...
Page 164: ...164 9 13 15 11 10 14 Extra 1 2 min 12...
Page 190: ...190...
Page 192: ...192 2016 1254 2014 A A ENERGIA ENERGIJA ENERGY ENERGIE ENERGI PINGVIN XL A 47 dB 340 m3 h...
Page 193: ...193...
Page 198: ...198...
Page 199: ...199 Enervent Zehnder Oy Kipin tie 1 FI 06150 PORVOO Tel 358 207 528 800 enervent enervent com...
Page 200: ...200...
Page 204: ...204 Enervent Zehnder Oy Kipin tie 1 FI 06150 PORVOO Tel 358 207 528 800 enervent enervent com...
Page 205: ...205 Enervent Zehnder Oy Kipin tie 1 FI 06150 PORVOO Tel 358 207 528 800 enervent enervent com...
Page 210: ...210...
Page 211: ...211...