COMMISSIONING
Requirements
For the ventilation unit to start running, it needs:
•
M8 °C return water temperature (if
applicable)
•
Supply and extract air below +55 °C.
For the ventilation unit to stay running, it needs:
•
M10 °C measured extract air temperature
•
Above +5 °C heat recovery supply air
•
Above +10 °C supply air temperature
•
All foreign objects removed from the ventilation
system.
•
Both fans operating.
Calibrating airflow
After the unit has been switched on, the airflows must
be calibrated to the planned values.
•
The airflow calibration is performed at start-up of
the ventilation unit.
•
The airflow calibration is done separately for both
fans for each mode selection (=fan speed) of the
ventilation unit.
When calibrating, make sure that:
•
All filters are clean
•
All supply and extract air valves, the roof pass-
through and the outside air grating are in place.
NOTE:
Do not cover the grating with a
mosquito net.
To achieve optimal values during calibration the
airflows must be measured at each duct opening. A
suitable measuring instrument is a thermo anemometer
or differential pressure meter. With the help of
registered values, airflow can be regulated to achieve
the projected values.
A correctly calibrated ventilation unit is quiet and gives
a good heat return and also upholds a small under-
pressure in the house. The underpressure prevents
humidity from entering the walls and ceiling.
Commissioning checklist
Item
Checked Notes
The unit has been
installed in its
place according
to the installation
instructions provided
by the manufacturer.
Condensate water
disposal pipe has
been connected to
the drain’s water lock
and tested.
Silencers have been
installed in the
supply and extract
air ducts.
For models with
water coils: dampers
have been installed.
All liquid coils are
connected, the liquid
flow(s) adjusted, and
the connections are
checked for leaks
All external valves
and valve actuators
are connected and
checked for correct
operation.
For CHG model:
coil, control valve,
valve actuator and
temperature sensor
for outside air duct
have been installed
and connected,
checked for correct
operation, and the
brine flow adjusted.
The freezing point
of the brine liquid
checked to be
sufficient.
Terminal devices
have been
connected to the
ventilation network.
Outside air grating
has been installed for
fresh air intake.
NOTE
: Do not cover
the grating with a
mosquito net. It will
make it very difficult
to clean.
Unit is connected
to an appropriate
electric supply.
Control panel has
been connected.
All external
sensors have been
connected and
checked for correct
operation.
The ventilation
ducts are insulated
according to the
ventilation plan.
Summary of Contents for eWind LTR-2
Page 1: ...12 7 2017 Enervent eWind Installation instruction ENG...
Page 48: ...48 Dimensional drawings Pinion right hand...
Page 49: ...49 Installation instructions EN Pinion left hand...
Page 50: ...50 Pingvin right hand...
Page 51: ...51 Installation instructions EN Pingvin left hand...
Page 52: ...52 Pingvin XL right hand...
Page 53: ...53 Installation instructions EN Pingvin XL left hand...
Page 54: ...54 Pandion...
Page 55: ...55 Installation instructions EN Pelican...
Page 56: ...56 Pegasos...
Page 57: ...57 Installation instructions EN LTR 2...
Page 58: ...58 LTR 3...
Page 59: ...59 Installation instructions EN LTR 4...
Page 60: ...60 LTR 6 25 mm...
Page 61: ...61 Installation instructions EN LTR 6 50 mm...
Page 62: ...62 LTR 7...
Page 63: ...63 Installation instructions EN Wiring digrams eWind basic wiring diagram...
Page 64: ...64 eWind basic wiring diagram Pingvin XL Pegasos and LTR 7...
Page 65: ...65 Installation instructions EN eWind basic external connections...
Page 66: ...66 eWind basic internal connections...
Page 67: ...67 Installation instructions EN eWind electrical heater 2kW...
Page 68: ...68 eWind electrical heater 2kW...
Page 69: ...69 Installation instructions EN eWind external electrical heater...
Page 70: ...70 eWind electrical pre heater...
Page 71: ...71 Installation instructions EN eWind extractor hood connections...
Page 72: ...72 Principal diagrams eWind HW principle scheme ESW_PRINCIPLE_SCHEME dwg...
Page 73: ...73 Installation instructions EN eWind CG principle scheme 1...
Page 74: ...74 eWind CG principle scheme 2...
Page 75: ...75 Installation instructions EN eWind CG principle scheme 3...
Page 76: ...76 eWind CG principle scheme 4...
Page 77: ...77 Installation instructions EN eWind CG principle scheme 5...
Page 78: ...78 eWind CG connections...
Page 80: ...80 eWind CHG principle scheme heat exchanger...
Page 81: ...81 Installation instructions EN eWind CW principle scheme...
Page 88: ...88 eWind CHG CHG eWind ELECTRICAL CABINET UNIT eWind_REV_A eWind CHG...
Page 93: ...93 Installation instructions EN...
Page 94: ...94...