22
Floor installation
Pandion, Pelican, Pegasos and Pegasos XL
Dimensional drawings for each of the models can be
found at the end of this manual.
To install:
1. Set the ventilation unit on the floor or on the
platform standing on its own rubber feet.
•
Make sure there is at least a 10 mm gap all
around the unit.
•
If the unit is installed with its side against a
wall, a 15 mm gap is required so the hatch can
be fully opened.
2. Note the space needed for disposing of
condensate water and the water trap under the
unit (if applicable).
•
Make sure there is at least 95 cm of space in
front of the unit’s maintenance hatch and
that the electrical connections can be easily
accessed.
3. Connect the unit to a condensate water disposal
drain with water trap.
4. Connect the ducts to the ventilation unit using
rivets.
5. Insulate the ducts according to the instructions in
Insulating ventilation ducts section.
6. Make the applicable electrical and plumbing
connections according to the electrical and
principal diagram at the end of this manual.
Installing models LTR-2, LTR-3,
LTR-4, LTR-6, LTR-7 and LTR-7 XL
Dimensional drawings for each of the models can be
found at the end of this manual.
Consult the ventilation planner regarding possible
need for additional insulation of the unit if mounted in
a cold space.
If you are using solid (hard) insulation, avoid fastening
the isolation in a way that conducts sound and
vibration to the house frame.
To install:
1. Set the unit on top of an insulating plate.
•
For example a chipboard covered with
100 mm of hard insulating wool – above the
rafters in the attic or on a separate shelf in a
storage etc.
2. Note the space needed for disposal of condensate
water and the water trap.
•
Make sure that there is enough space left in
front of or above the maintenance hatch:
•
Tilt the unit slightly in the direction of the
condensation drain.
Unit
Free space
LTR-2 and LTR-3
min. 50 cm
LTR-4 and LTR-6
min. 60 cm
LTR-7 and LTR-7 XL
min. 70 cm
3. Note the space needed for opening the
maintenance hatch locks.
•
Make sure the electrical connections can be
easily accessed.
4. Connect the ducts to the ventilation unit with
circular duct fittings using rivets.
5. Insulate the ducts according to the instructions
in chapter "Insulating ventilation ducts" on page
11.
6. Connect the unit to a condensate water disposal
drain with water trap.
•
If the ventilation unit is equipped with a
built-in cooling coil it is recommended to
install the unit with the service hatch to the
side to enable the condensate water to drain
more easily.
•
LTR-4 units with cooling coil have two optional
32 mm condensation drains. One drain is
welded shut and the other is ready to use.
Depending on the way the LTR-4 unit is
installed, the drain that becomes lower is to
be used. If the lower drain is the welded one,
a short piece of the pipe is sawed off to open
the pipe, and the water trap is connected to
the pipe.
•
The unused condensation drain must be
plugged.
7. Make the applicable electrical and plumbing
connections according to the electrical and
principal diagram at the end of this manual.
Installing model eWind W
Principal, control and wiring diagrams for each model
can be found at the end of this manual.
Check the principal charts for units with fluid coil. Install
and connect the water pipes according to these charts.
To install:
1. Install the dampers and damper motors.
2. Install and connect the water pipes.
3. Install the valve and the valve actuator.
Summary of Contents for eWind LTR-2
Page 1: ...12 7 2017 Enervent eWind Installation instruction ENG...
Page 48: ...48 Dimensional drawings Pinion right hand...
Page 49: ...49 Installation instructions EN Pinion left hand...
Page 50: ...50 Pingvin right hand...
Page 51: ...51 Installation instructions EN Pingvin left hand...
Page 52: ...52 Pingvin XL right hand...
Page 53: ...53 Installation instructions EN Pingvin XL left hand...
Page 54: ...54 Pandion...
Page 55: ...55 Installation instructions EN Pelican...
Page 56: ...56 Pegasos...
Page 57: ...57 Installation instructions EN LTR 2...
Page 58: ...58 LTR 3...
Page 59: ...59 Installation instructions EN LTR 4...
Page 60: ...60 LTR 6 25 mm...
Page 61: ...61 Installation instructions EN LTR 6 50 mm...
Page 62: ...62 LTR 7...
Page 63: ...63 Installation instructions EN Wiring digrams eWind basic wiring diagram...
Page 64: ...64 eWind basic wiring diagram Pingvin XL Pegasos and LTR 7...
Page 65: ...65 Installation instructions EN eWind basic external connections...
Page 66: ...66 eWind basic internal connections...
Page 67: ...67 Installation instructions EN eWind electrical heater 2kW...
Page 68: ...68 eWind electrical heater 2kW...
Page 69: ...69 Installation instructions EN eWind external electrical heater...
Page 70: ...70 eWind electrical pre heater...
Page 71: ...71 Installation instructions EN eWind extractor hood connections...
Page 72: ...72 Principal diagrams eWind HW principle scheme ESW_PRINCIPLE_SCHEME dwg...
Page 73: ...73 Installation instructions EN eWind CG principle scheme 1...
Page 74: ...74 eWind CG principle scheme 2...
Page 75: ...75 Installation instructions EN eWind CG principle scheme 3...
Page 76: ...76 eWind CG principle scheme 4...
Page 77: ...77 Installation instructions EN eWind CG principle scheme 5...
Page 78: ...78 eWind CG connections...
Page 80: ...80 eWind CHG principle scheme heat exchanger...
Page 81: ...81 Installation instructions EN eWind CW principle scheme...
Page 88: ...88 eWind CHG CHG eWind ELECTRICAL CABINET UNIT eWind_REV_A eWind CHG...
Page 93: ...93 Installation instructions EN...
Page 94: ...94...