Cerabar PMP23 IO-Link
Commissioning
Hauser
23
9
Commissioning
If an existing configuration is changed, measuring operation continues! The new or
modified entries are only accepted once the setting has been made.
L
WARNING
Risk of injury from the uncontrolled activation of processes!
‣
Make sure that downstream processes are not started unintentionally.
L
WARNING
If a pressure smaller than the minimum permitted pressure or greater than the
maximum permitted pressure is present at the device, the following messages are
output in succession:
‣
S140
‣
F270
9.1
Function check
Before commissioning your measuring point, ensure that the post-installation and post-
connection check have been performed:
• "Post-installation check" checklist → 16
• "Post-connection check" checklist → 18
9.2
Commissioning with an operating menu
Commissioning comprises the following steps:
• Configure pressure measurement → 24
• If necessary, perform position adjustment→ 26
• If necessary, configure process monitoring → 28