7
Testing
7.1
Test the turbine meter
7.1.1
Commission the turbine meter
After installation, commission the turbine meter to ensure that the equipment is working
properly.
Procedure
1. Inspect all electrical connections to ensure compliance with electrical codes and
safety regulations.
2. Inspect all flange bolts used to secure the turbine meter in-line to ensure that
correct mounting procedures are followed and that flange connections are leak-
free.
3. Evaluate the system setup to ensure that all components are in the correct
sequence for accurate product measurement: isolation valve, strainer, flow
straightener, turbine meter, downstream section, control valve, etc.
4. Ensure that the supply voltage to the preamplifier is within the 10-30 VDC range.
User manual
Testing
P/N 3-9008-515
March 2019
User manual
77
Summary of Contents for Daniel Series
Page 2: ...2 ...
Page 11: ...Part I Plan User manual Plan P N 3 9008 515 March 2019 User manual 11 ...
Page 69: ...Part II Install User manual Install P N 3 9008 515 March 2019 User manual 69 ...
Page 79: ...Part III Operate User manual Operate P N 3 9008 515 March 2019 User manual 79 ...
Page 83: ...Part IV Maintain User manual Maintain P N 3 9008 515 March 2019 User manual 83 ...
Page 105: ...User manual P N 3 9008 515 March 2019 User manual 105 ...