Replacing the Power Supply Board
Section 3: Meter maintenance
Maintenance and Troubleshooting Manual
January 2018
3-9000-772 Rev B
12.
Connect to the meter with Daniel MeterLink. Open the Meter Monitor (Detailed) view
and verify the meter is acquiring data, the transducers have good signals and flow
profiles for the chords are displayed and run the Zero Flow Calibration Wizard; select
the
Calibrate|Zero Calibrate
menu and generate the report. Then, collect and save a
Maintenance log to show the “as left” condition of the meter.
Or use AMS
TM
Device Manager or a HART® Field Communicator and select
Overview
|Zero Calibration|Start
menu or
Service Tools|Maintenance| Zero Calibration
|
Start.
13.
Close your application connection (Daniel MeterLink, AMS
TM
Device Manager or HART®
Field Communicator).
14.
If replacing other electronics, see
Section 3.4.2
through
Section 3.4.5
before replacing
the end caps and sealing the enclosure.
15.
If you are not replacing other electronics, replace the Transmitter Electronics Enclosure
end caps, install the end cap security latches (3mm Allen wrench required). If required,
install the security seals (
see Section 3.6.1
and
Section 3.6.2
).
16.
Apply power to the meter.
17.
This completes the Power Supply Board replacement procedure.
18.
If you encounter problems with this procedure, see the Daniel Customer Service
contact information on the back cover of this manual.