2 Securing the roof bars
Firstly thread the glazing bead into both grooves of each roof glazing bar, as previously described in
an earlier section.
Starting at one end (your choice).
1.
Slide 4 bolts along the bolt slot of each roof glazing bar. Add an extra bolt to the roof bars
onto which the roof vents will be fitted. Please note the roof vent must be fitted between 2
roof glazing bars. It cannot be fitted to an end or partition corner bar. Add the nut and finger
tip tighten.
2.
From the top of the glazing bar (and all other glazing bars when you arrive at that stage), slide
1 bolt down the bolt slot, and attach to the prefabricated hole in the ridge bar.
3.
Then repeat at the bottom of each roof glazing bar and attach to the gutter bar.
4.
Attach all the other glazing bars to the gutter and ridge in the exact same way as above.
5.
Tighten all the nuts taking care not to over tighten.
3 Sliding the vent into position
The hinge is a groove ball and socket joint, the socket is an integral part of the ridge, the ball being
a part of the vent top rail
(Key point).
You must identify correctly these two sections.
Then slide the vent on to the ridge from one end. With the vent in the open position, push the vent
along the ridge until it covers the middle section (if your greenhouse is more than 3 panes long you
must decide which section the vent is to be situated in). The two side rails of the vent will overlap
the outside edges of the middle two roof bars.