Regarding the partition, you need do nothing more at this stage. When the greenhouse is fully con-
structed and anchored to the wall and base, you build the partition in situ and not as an independent
frame.
(Key point).
Procedure:
1.
Insert the glazing bead in to the gutter/eave bar and glazing bars
as shown below (in the
manner previously outlined).
2. Lay out the component parts on the floor with the bolt slots uppermost. The
gutter and cill are facing the ground.
3. Insert 3 bolts into each glazing bar (1 – top, 1 – middle, 1 – bottom). If you
are fitting a front door, insert an extra bolt into the top of each glazing bar that
form the door opening. These will be used later in the installation of the door.
4. For double doors, do not fit a glazing bar in the centre of the door way. i.e.
vertical bar No 2 on the picture is not supplied or fitted.
5. Attach the gutter/eave bar to the top of each glazing bar utilising the top bolt
in each glazing bar as illustrated.
6. The bottom cill will bolt to the bottom of the glazing
bars in a similar manner. Before securing the nut on to
the bottom bolt of the outer glazing bars, place the di-
agonal brace angles over the bolt. The bracing angles
must be arranged so that the inside of the angles are
facing each other.
7. Attach the horizontal angle brace utilising the previ-
ously inserted bolts and position the bar around the
middle of each glazing bar. Ensure that the horizontal
angle brace is parallel to the gutter/eave bar and cill.
8. Ensure all points are tight and frame is square before
tightening nuts.
9. Front frame assembly is now complete.