Procedure
1. The initial construction of this gable is identical to the right hand gable except for the changes
listed below. Door end does not consist of louvre or shelf. The diagram below shows the bolt con-
figuration for the door end. (Again a dot indicates a bolt).
N.B.
If your door is on the front, (parallel to the wall) then repeat the bolt configuration for R H
end (except for shelf and louvre bolts).
On the door end there are a combination of short bracing angles to be fitted which can be found in
the main box marked DOOR END.
2. These four bars like the horizontal bracing angle, can be fixed either upwards or downwards (for
aesthetic reasons we suggest that you attach them the same way as horizontal bracing angle). Using
the previously inserted bolts, attach the short bracing angle to the unit
as shown (exact distances are not required). Put nuts back on and fin-
ger tip tighten all three bars.
3. The door track support looks similar to a ‘Z’ bar (see component
drawings at beginning of booklet). The door track support is fitted on
2nd and 4th glazing bars from the wall, using the two remaining unoc-
cupied nuts and bolts. The end slotted holes must face upward like a
letter ‘U’ (see diagram).
Key Point.
4. Tighten all nuts remembering not to over tighten. The door track support may need altering
slightly in the construction, so finger tip tight will be sufficient at this stage.
N.B.
Do not fit the door track at this stage – this will be done later in General Assembly.
DOOR TRACK SUPPORT