![EcoFasten Clickfit Installation Manual Download Page 28](http://html1.mh-extra.com/html/ecofasten/clickfit/clickfit_installation-manual_2354081028.webp)
VERSION: v3.0
REVISION DATE: 12/2/22
INSTALLATION GUIDE
ACCESSORIES
DECK SCREWS WITH
SEALING WASHERS (2X)
PAGE
27
JUNCTION BOX INSTALLATION
DECK MOUNTED INSTALLATION
For conduit that will go into the attic, place the box and flashing in a position that avoids
rafters and single joints. Slide the flashing under the shingle course and align the bottom
of the box with the flashing. an EPDM foam gasket is pre installed to the underside of the
junction box to seal the box and flashing together once compressed. no additional sealant is
required. secure the supplied (2x) #12x3” deck screws until the junction box is pulled tight to
the flashing. Do not over torque screws to avoid stripping the screws in the decking.
*If installing pass through fittings, ensure that the Junction Box and roof deck are both properly prepared. Complete installation
process before attaching the Junction box to the deck.
FINALIZING INSTALLATION
Install wiring, conduit and fittings per NEC requirements and following local AHJ guidance.
Using Philips Head Driver tighten the bolt.
For additional details refer to the full Junction Box Installation Manual.