Step 5.

 

Tighten the joint pack assembly using a 19mm spanner until the 

shear nut breaks and the indicator disk drops off then tighten 

to 65Nm ±5Nm using a calibrated torque wrench with a 19mm 

socket. If installed correctly the joint will appear level and no 

overlapping should appear. If overlapping of the Expansion 

Ribs is apparent then the joint is not installed correctly.

The shear nut will break when torqued to 65Nm ±5Nm in a 

clockwise direction. This will cause the indicator disc to fall off.

Step 6. 

Megger the installed joint pack to ensure it is fi tted correctly.

Following a visual inspection to ensure that there are no 

anomalies such as foreign material etc, install the front 

joint pack cover. 

Joint pack cover

Sign & date the label on the joint cover 

for the quality control records.

Joint Pack Elbow

Ensure all parts are meggered and visually inspected 

prior to installation.

Step 1. 

Mount Busbar to frame.

Step 2.

Install the Joint Pack Elbow to Busbar, never force the joint 

or strike it with any object as this may damage the Joint or 

Busbar section. The joint should be inserted by means of 

a constant force, i.e. pushing in by hand or by means of a 

suitable clamping arrangement.

Step3.

Position second busbar as shown in image overleaf. Ensure 

the Earth Side Plates are not over lapping the Expansion Ribs. 

The Earth side plates should sit approx 2mm back from the 

Expansion Rib when positioned correctly.

Step 4.

Mount the second Busbar section fi rmly to the frame work.

Step 5.

Attach the rear Joint Pack Cover to Parts.

Step 6.

Tighten the Joint Pack assembly to the correct torque level 

(65Nm ±5Nm). If installed correctly the joint will appear 

level and no overlapping should appear. If overlapping of 

the Expansion Ribs is apparent then the Joint is not installed 

correctly.

Step 7.

Megger the installed joint pack to ensure it is fi tted correctly. 

This is on a visual inspection for any anomalies such as 

foreign material etc. Now attach the front Joint Pack Cover to 

the Busbar.

Summary of Contents for Power Xpert XP2

Page 1: ...Power Xpert XP2 Power Xpert XP2 Installation Manual Installation Manual www eaton eu busbars OHSAS 18001 2007 OHS 533652 ISO 9001 2008 FM 12680 ISO 14001 2004 No EMS 566536...

Page 2: ...ot exceed the safe working load of the lifting apparatus Ensure that equipment is used as per manufacturer s guidelines Storage The Busbar will be delivered to the customer neatly stacked on a wooden...

Page 3: ...ific area Eaton recommend that the fixing brackets must be mounted no more than 500mm from the centre of the joints For vertical riser installation of sections greater than 2 metres it may be easier t...

Page 4: ...t is the responsibility of the support system supplier to ensure their system can safely support the weight of our product Please note Eaton fixing bracket s must be used Drilling or cutting the busba...

Page 5: ...to Unistrut with M10 Hex Bolt and Lock Nut tighten the bolts to 45Nm 5Nm Step 4 Attach Spring Hanger Brackets to Busbar using fixing brackets Step 5 Tighten the joint pack to 65Nm 5Nm once the spring...

Page 6: ...ntact surfaces are free from contaminates unblemished not damaged correctly aligned Step 4 a Position Busbar B as shown in the image Ensure that the Earth side plate is not overlapping the Expansion R...

Page 7: ...on Step 1 Mount Busbar to frame Step 2 Install the Joint Pack Elbow to Busbar never force the joint or strike it with any object as this may damage the Joint or Busbar section The joint should be inse...

Page 8: ...EATON wb xp2 en 8...

Page 9: ...e required to install the Cable End Box following the instructions shown Unistrut rail Access cover Gland plate 2 3 M10 Channel Nut M10 Bolt 1 Unistrut rail 2 Access cover 3 Gland plate Tap Off Cover...

Page 10: ...ng brackets Step 4 Offer the tap off box up to the shutter housing and visually line up the earth contact bracket and actuator to ensure correct location of the tap off contacts The box cannot be inse...

Page 11: ...sitive ON OFF operation Examine protective device for sign of short circuit operation If a short circuit has occurred on the equipment connected to the tap off module check operation of device and the...

Page 12: ...aton eu Eaton Electric Ltd 270 Bath Road Slough Berkshire SL1 4DX Tel 01753 608 700 Email systemquotes eaton com www eaton com To contact an Eaton salesperson or local distributor agent please visit w...

Reviews: