Cable End Box
This is generally the fi rst component to be mounted on a rising busbar.
The entire route should initially be inspected for any obstructions before installation.
The box should be installed at the correct height in accordance with the approved
drawings.
A plumb line should be applied at this point from the start of the run to the end of
the run, as a guide for the vertical installation of the Busbar Run.
4 of M10x20 bolts c/w Bellville washers and a 17mm socket are required to install the
Cable End Box following the instructions shown.
Unistrut rail
Access cover
Gland plate
2
3
M10 Channel Nut
M10 Bolt
[1] Unistrut rail
[2] Access cover
[3] Gland plate
Tap Off Cover
Busbar
Tap Off Slot Cover
Distribution Busbar lengths are available with up to 5 tap
off positions on a 3 metre length.
Each tap off position is IP2X in accordance with IEC61439-2.
With a standard tap off installed the rating is IP54 but this can
be improved if required.
A cover is required over unused tap off positions to increase
the ingress protection (IP) level to the required standard.
When
fi tting a new tap off, this cover is to be removed.
The drawing opposite shows the removal of the cover
.
Summary of Contents for Power Xpert XP2