7
Installation Guide
GREEN MOTION FLEET & BUILDING
www.eaton.com
Reference:
1
.
Lineside conductors
2
.
Junction box
3
.
Conductors from circuit breakers
4
.
Junction box cover
Insert the lineside conductors
(1)
into the junction
box
(2)
.
Run conductors
(3)
from the circuit breaker to the
junction box and connect inside the junction box .
Suggest using the Polaris lugs provided in the kit
for wiring inside the junction box .
Secure the cover of the junction box
(4)
.
STEP B-5
1
4
3
2
Feed the lineside conductors
(1)
from the EV charger
(2)
through a 1” trade size conduit (not included)
(3)
.
STEP B-4
Reference:
1
.
Lineside conductors
2
.
EV charger
3
.
1” trade size conduit
1
2
3
Follow local guidelines to secure the cover
and knock-out holes of the junction box.
!