13
Installation Guide
GREEN MOTION FLEET & BUILDING
www.eaton.com
Push the conduit
(1)
into the
90-degree conduit fitting
(2)
Feed the conductors and the
threads of the 90-degree conduit
fitting
(2)
through the small
cutout on the pedestal
(3)
.
Use the plastic nut
(4)
to secure
the fitting in place .
Cut the L1 and L2 charger conductor to the desired
lengths and connect them with their respective
power cables using two Polaris lugs
(1)
.
Install a ring terminal on the EV charger ground
conductor and connect it to the pedestal ground
stud
(1)
. Secure the ring terminal to the pedestal
ground stud using a 1/4-20 serrated flange nut .
STEP C-9
STEP C-10
STEP C-11
Reference:
1
.
10.5” conduit
2
.
90-degree conduit fitting
3
.
Small opening in pedestal
4
.
1/2” plastic nut
Reference:
1
.
Polaris lugs
Optional
Reference:
1
.
EV charger ground conductor
2
1
3
4
READY
CHARGE
FAULT
L2
L2
L1
GROUND
L1
1
1