Suggested Customer Acceptance Test Checklist
Mechanical
Check all cabling is routed to specifications
Check dc supply cables from rack as specified for connection to load
Check mounting of rack and battery stand is to plans and specifications
Check clearances around the installed equipment are to plan
Check earth (ground) and insulation visually and with meters
Batteries (if supplied by your Eaton dc product representative)
Battery capacity check
Supervisory Module
Configuration as in Configuration Printout (or as modified at customer’s request)
— see Note below
Check password access as specified
Compare system controller current/voltage readings against metered readings
(Ensure meters connected at correct points)
Check communication to rectifiers
System Control Processes
Check active voltage control (if configured)
Simulate temperature compensation
Check manual equalize (if configured)
Check periodic equalize (if configured)
Check fast charge (if configured)
Check low voltage disconnect (if configured)
Check current sharing (if configured)
Remote Communications
Check system controller communications with remote software application
Check auto dial-out and auto dial-in functions if modem installed