Installation
Eaton BladeUPS 12 kVA Maintenance Bypass Cabinet Installation and Operation Manual P-164000130—Rev 1
www.eaton.com/powerquality
3-5
Figure 3-3. Lifting the MBC from the Pallet
3.
Set the cabinet down in the installation site.
4.
Move the forklift away from the cabinet.
5.
Align the cabinet to the floor anchors and secure the MBC in a stabilized position.
6.
Reinstall the vent covers at the bottom of the front and back door (see Figure 3-1). Using a nut driver,
secure each vent cover with two
1
/
4
–
20
x
1 1/2-inch hex head screws.
7.
Lift up the front door key latch. Turn it to the right and pull open the front door.
8.
Use a screwdriver to pry the hinge pins from each of the three front door hinges. Lift the front door off of
the hinges and set the door aside. Retain the front door and the hinge pins for reinstallation.
9.
Locate the retaining screws on both the top and bottom inside the distribution panel doors. Remove the
four retaining screws that secure each door panel, then remove the door panels. Retain the door panels
and retaining screws for reinstallation.
10. Discard or recycle the pallet and shipping material in a responsible manner.
3.2
Connecting Power Wiring
.
NOTE
Remove the MBC conduit landing plate (either top or bottom) to drill or punch
conduit holes. See Appendix A.2 “Installation and Wiring Diagram” in this manual.
NOTE
Refer to the
Eaton
®
BladeUPS
®
User’s Guide (Preassembled and Standard Systems)
For use with Eaton BladeUPS 5.1 kVA to 60 kVA (N+1) systems
for UPS cabinet
wiring information, conduit locations, and terminal locations.
To connect the MBC power wiring:
Summary of Contents for BladeUPS none
Page 65: ......
Page 66: ...164201690 4 P 164000130 1...