INSTALLATION, OPERATION AND MAINTENANCE MANUAL
Easco Boiler Corp 1175 Leggett Ave Bronx, NY 1047 T: 718.378.3000 F: 718.378.4560 [email protected] easco.com
Page 24 of 46
3) Add solution through the exposed tapping and then reinstall safety valves.
4) Fill the entire system with water.
5) Start firing the Boiler.
6) Circulate the water through the entire system.
7) Vent the system, including the radiation.
8) Allow boiler water to reach operating temperature, if possible.
9) Continue to circulate the water for a few hours.
10) Stop firing the Boiler.
11) Drain the system in a manner and to a location that hot water can be discharged
with safety.
12) When the Boiler has cooled down to 120 °F or below, remove plugs from all
available tappings and thoroughly wash the waterside of the Boiler with a high-pressure
water stream.
13) Refill the system with fresh water and bring water temperature to 180 °F or above
promptly to drive off any dissolved gases in the fresh water.