background image

INSTALLATION, OPERATION AND MAINTENANCE MANUAL

Easco Boiler Corp     1175 Leggett Ave Bronx, NY 1047     T: 718.378.3000     F: 718.378.4560     [email protected]      easco.com

Page 41 of 46

devices. It is important that inspections are thorough and complete, and so those 
important elements may be all checked. The following recommended directions and 
instruction for such inspections are given.

a)   All Boilers should be prepared for inspection, whenever necessary, by the owner 
or user when notified by the inspector. The owner or user should prepare for and apply 
the hydrostatic test whenever necessary on the date specified in the presence of the 
authorized inspector.

b)   Before inspection, every part of a Boiler that is accessible should be open and properly 
prepared for examination, internally and externally. In cooling down a Boiler for inspection 
or repairs, the water should not be withdrawn until the setting is sufficiently cooled to avoid 
damage to the Boiler, and when possible, it should be allowed to cool down naturally.

c)   Preparation – The owner or user should prepare a Boiler for internal inspection in the 
following manner:

1) Water should be drained and Boiler washed thoroughly.

2) All man-hole and hand-hole plates, washout plugs and water column 
connections should be removed and the furnace and combustion chambers 
thoroughly cooled and cleaned.

3) All grates of internally fired Boilers should be removed.

4) Brickwork should be removed, as required by the inspector, in order to determine 
the condition of the furnace, supports or other parts.

5) Any leakage of water into the Boiler should be cut off by disconnection the pipe 
or valve at the most convenient point.

d)   It is not necessary to remove insulation material, refractory or fixed parts of the 
Boiler unless defects or deterioration are suspected. Where there is moisture or vapor 
showing through the covering, the covering should be removed at once a complete 
investigation made. Every effort should be made to discover the true condition, even if it 
means drillings holes or cutting away parts.

e)   The inspector should get as close to the parts of the Boiler as is possible in order to 
obtain the best possible vision of the surface and to use a good artificial light if natural 
light is not adequate.

f)   Whenever the inspector deems it necessary to test boiler apparatus, controls, etc., 
these tests should be made by a plant operator in the presence of the inspector, unless 
otherwise ordered.

g)   Scale, Oil, Etc. – The inspector should examine all surfaces of the exposed 
metal inside to observe any action caused by treatment, scale solvents, oil or other 

Summary of Contents for FST Series

Page 1: ...PLW 3 Pass Series FPS 4 Pass Water backed Steel Horizontal Firetube Boilers Manufactured in Accordance to Current Approved Edition of the ASME Boiler and Pressure Vessel Code Section IV Rules for the...

Page 2: ...ble efficient service All components of Equipment were chosen for their ability to enhance this design goal Although these components provide high degree of protection and safety during normal operati...

Page 3: ...3 2 ASME Name Plate 12 3 3 Manufacturer s Data Report 12 3 4 Configurations 13 SECTION 4 INSTALLATION INSTRUCTIONS 14 4 1 Inspection of Equipment Shipment 14 4 2 Placement Setting of Equipment 15 4 3...

Page 4: ...urfaces 33 6 3 General Maintenance Considerations 35 6 4 Repair Parts 36 SECTION 7 WATER TREATMENT 37 7 1 Boiler Water Treatment Considerations 37 7 2 Make pH or Alkalinity Test 37 7 3 Services of Wat...

Page 5: ...t be maintained and operated only by competent and qualified operating and service personnel who are fully trained and thoroughly familiar with same equipment system application and ancillary support...

Page 6: ...plicable Codes and Standards of the most current approved and or accepted Editions governing the design handling installation commissioning operation care and continued maintenance of such equipment i...

Page 7: ...nd all combustible materials such as rags paper wood paint or other debris shall be kept clear of boiler room environs Boiler room shall be kept clean and free of fire hazards 8 Safety Precautionary N...

Page 8: ...llons Per Minute Horsepower Inches Pound s Lowest Permissible Water Level Low Water Cut Off Maximum Allowable Work Pressure Maximum Allowable Work Temperature Master Bill Thousands of BTUH Manufacture...

Page 9: ...ceed the minimum efficiency criteria and requirements of ASHRAE Standard 90 1 Energy Standard for Buildings Except Low Rise Residential Buildings I P Edition This Manual provides the required informat...

Page 10: ...per and safe installation commissioning operation care and continued maintenance of the Equipment 2 2 Operation Care and Continued Maintenance Qualification Operation care and continued maintenance of...

Page 11: ...es as published by Manufacturers of any and all component part of this Equipment must be adhered to assure the proper and safe design handling installation commissioning operation care and continued m...

Page 12: ...5 and to the front tube sheet of a Firebox Vessel at about 90 This Stamp Plate includes information explicitly Certified By the Manufacturer regarding MAWP and MAWT heating surface area minimum relief...

Page 13: ...width reversing chamber also completely submerged within water contained in the vessel shell a therefore narrow width firetube layout pattern an relatively extended vessel length to compensate the sm...

Page 14: ...ure by the transportation carrier agent of this eat time of delivery regardless of any dispute which may ensue with transportation carrier agent regarding Equipment condition or shortage 4 1 5 Equipme...

Page 15: ...Equipment shall be so located as to provide for proper venting and adequate clearances and means for general access inspection maintenance serviceability and installation of field piping and electric...

Page 16: ...nt positive pressurization of breeching and chimney systems during normal operation Breeching and chimney systems shall be designed installed and maintained in a manner as to prevent any source of lea...

Page 17: ...During cold start up procedures condensation will likely occur until Equipment reaches operating temperature limits If condensation persists the low temperature or pressure limit or fuel input turn d...

Page 18: ...sure Gauge of 4 1 2 in dial 0 30 PSIG ASME accuracy ASME Safety Valve s 4 6 2 STANDARD WATER TRIM McDonnell Miller No 63 M MAWP 50 PSIG or No 150S MAWP 150 PSIG Float Type LWCO with Manual Reset or PS...

Page 19: ...mended by its manufacturer 4 8 2 The following guidelines should be followed when piping tankless heater a FLOW REGULATION If flow through the heater is greater than it s rating the supply of adequate...

Page 20: ...If a local water treatment company is going to be part of your boiler maintenance program they should be contacted for recommendation as to what boil out chemicals they recommend and how they will af...

Page 21: ...the firesides and become evident at the drains provided in the smoke boxes This is normal and should not be cause for alarm 12 Operate the Boiler as though in conventional service reaching normal ope...

Page 22: ...9 5 The Boiler must be fired at a low rate for at least one day to dry out the refractory linings Adjust the firing apparatus for a low firing rate and operate intermittently to keep combustion chambe...

Page 23: ...r can be discharged with safety 6 When the Boiler has cooled down to 120 F or below refill it to the normal water line If water in gauge glass does not appear to be clear repeat steps 1 through 5 abov...

Page 24: ...ing the radiation 8 Allow boiler water to reach operating temperature if possible 9 Continue to circulate the water for a few hours 10 Stop firing the Boiler 11 Drain the system in a manner and to a l...

Page 25: ...oilers Top of lower gauge glass nut lowest visible water level must be located 3 in above the top of the highest firetube projection 5 1 2 Section IV Low Pressure Heating Boilers Top of lower gauge gl...

Page 26: ...state local and insurance regulations 5 3 3 Adjust burner according to the burner manufacturer s specifications Refer to burner manufacturer s Installation Operation and Maintenance Manual furnished...

Page 27: ...sed to possible contamination in the boiler water and subject to fouling It is important to physically remove the probe from the boiler tapping annually and inspect that probe for accumulation of scal...

Page 28: ...nel to the extent necessary to insure freedom from obstructions and proper functioning of the working parts Inspect connecting lines to Boiler for accumulation of mud scale etc and clean as required E...

Page 29: ...Boiler The use of the blow off or drain valve in a low pressure heating Boiler is for discharging rust colored water and sediment which settles to the bottom of the Boiler Quantity and frequency of b...

Page 30: ...r size 5 9 3 The return water temperature should always be within 40 F to the supply temperature 5 9 4 Return water temperature should be continuously monitored Anytime when the return water temperatu...

Page 31: ...e fluctuation and flow through the Boiler must be observed 5 10 1 It is important to operate your Boiler in such a manner as to prevent temperature fluctuation of more than 40 F at any time Rapid temp...

Page 32: ...at the same time 6 1 2 Have burner and controls checked at least once a year or as may be necessitated 6 1 3 Retain your contractor or a competent serviceman to assure that the unit is properly adjust...

Page 33: ...f relief must be investigated and corrected Excess pressure is dangerous and can cause damage to the heating system personal injury and serious property damage 6 2 5 DO NOT draw water from Boiler whil...

Page 34: ...e to heat system to high temperature and vent again This will make less venting necessary during the winter 6 3 4 Where an expansion tank is used makes sure that neither the tank nor its drainpipe is...

Page 35: ...718 378 4560 info easco com easco com Page 35 of 46 6 4 Repair Parts Give Boiler Series and Model Number when ordering repair parts All repair parts can be ordered through the commercial sales office...

Page 36: ...efilled as previously described test the pH of the water in the system This can easily be done by drawing a small sample of boiler water and testing with hydroid paper which is used in the same manner...

Page 37: ...he water is soft this makes the water acidic and corrosive The boiler metal and condense return lines will be attacked This can be general overall corrosion or localized pitting or cracking in stresse...

Page 38: ...still recognized as one of the best inhibitors for protection of metal although it is now prohibited by most states or cities for use as water treatment due to the toxic effect of the chromate when du...

Page 39: ...litmus paper except it gives specific readings A color chart on the side of the small hydroid dispenser gives the reading in pH Hydroid paper is inexpensive and obtainable from any chemical supply hou...

Page 40: ...ses in load sudden pressure drop In case of serious trouble stop the burner and decrease the load on the Boiler until the true level can be determined Then alternately blow down and feed fresh water s...

Page 41: ...plates washout plugs and water column connections should be removed and the furnace and combustion chambers thoroughly cooled and cleaned 3 All grates of internally fired Boilers should be removed 4...

Page 42: ...rfaces Bulging Blistering Leaks Particular attention should be given to the plate or tube surface exposed to fire The inspector should observe whether any part of the Boiler has become deformed during...

Page 43: ...essive vibration o Low Water Cut Off All automatically fired Boilers are required to be equipped with an automatic low water fuel cutoff so located as to automatically cut off the fuel supply when the...

Page 44: ...d by the inspector a hydrostatic test shall not exceed that specified by applicable code During the test the safety safety relief valve should be removed from the Boiler as should all controls and dev...

Page 45: ...port came with the Boiler to be repaired 8 3 Safety Every precaution must be taken to insure against injury to personnel who are working in the boiler room and particularly to those working inside the...

Page 46: ...INSTALLATION OPERATION AND MAINTENANCE MANUAL Easco Boiler Corp 1175 Leggett Ave Bronx NY 1047 T 718 378 3000 F 718 378 4560 info easco com easco com Page 46 of 46 NOTES...

Reviews: