3
2.4 Available Load Steps (Model Specific)
Available Load Steps (at rated voltage)
LB-10kW
4 Steps – 1, 2, 2, and 5 kW
LB-30kW
6 Steps – 1, 2, 2, 5, 10, and 10 kW
LB-40kW
6 Steps – 1, 2, 2, 5, 10, and 20 kW
LB-50kW
7 Steps – 1, 2, 2, 5, 10, 10, and 20 kW
LB-100kW
8 Steps – 1, 2, 2, 5, 10, 10, 20, and 50 kW
LB-200kW
7 Steps – 5, 5, 10, 10, 20, 50, and 100 kW
LB-300kW
8 Steps – 5, 5, 10, 10, 20, 50, 100, and 100 kW
LB-500kW
9 Steps – 5, 5, 10, 10, 20, 50, 100, 100, and 200 kW
LB-800kW
10 Steps – 5, 5, 10, 10, 20, 50, 100, 200, 200, and 200 kW
LB-1000kW
11 Steps – 5, 5, 10, 10, 20, 50, 100, 200, 200, 200, and 200 kW
2.5 Measuring Control Function
Load testing
: Can provide load power
up to the model’s rated power, test and display
stable state 3 phase voltage, current, active power, frequency, and working time of
generator sets.
Load/unload with one key:
Whether manual control or software control, user can preset
the power, then press load master button. Loading is according to preset power to avoid
load fluctuation during the power changing.
Control Pattern:
User can choose between local control and intelligent control.
Local control
: There is a local control panel with several power steps available; user can
load/unload as necessary by these buttons.
Intelligent control
: Through PC software, user can set automatic loads and display,
record, and manage testing data. User can also form curves, tables, and print reports.
Local meter display data:
Displays
3 phase voltage, current, active power, frequency, etc.
2.6 Software Function
Communication pattern
: The intelligent control uses a photoelectric isolated RS485
interface connected to PC with anti-interference technology to make system control
stable. Users can also use USB or RS232 through a converter.
Load pattern:
Manual Load or Automatic Load.
Manual Load:
System will load according to preset power.