Shows the total apparent energy, the first line shows the symbol ES, second, a 

combination of three lines into eight data show power when the unit kVA displayed. 

Note: In addition to the above features, do not perform other operations on the 

measuring meter. Incorrect settings can result with inaccurate data. If the meter does not 

work properly or shows inaccurate data, please contact Eagle Eye Power Solutions 

4.6 Protection 

(1) Emergency Manual: 

If an emergency happens, please immediately press the red

[EMERGENCY STOP] 

switch. The machine will remove the load. Emergency indicator 

lights up and beeps alarm. In this state the load function is locked out and only the fan 

continues to run. After an emergency is corrected, the emergency stop switch can be 

rotated clockwise to unlock for testing to resume.   

(2) Automatic protection: 

This machine has an automatic protection function. When the

following circumstances occur the fault and the corresponding alarm indicator lights and 

alarm engage. Protection status loading function is locked. Identify the reasons for 

troubleshooting and once resolved release and re-test the alarm.   

Overheating

: The internal temperature exceeds a preset warning level;   

Overvoltage

: The machine input voltage exceeds a preset warning level;   

Some of the protective functions have a switch, and when the protection switches point 

downward, it can safely give alarm. When the protective functions give false alarms, or 

require temporary removal of some protection functions, then pull up on the appropriate 

protection switch to turn off protection. Then under the same condition, unit will not give 

the corresponding alarm and instead continues load testing.   

Attention: If there are no special needs for testing, be sure to keep the protection 

switches in downward position so that protection is active. 

4.7 Shutdown 

 

Let fans continue running for about 3 - 5 minutes to disperse the heat inside the chassis. 

Then turn off the power switch on the control panel to stop the fan. Finally, turn off the 

Summary of Contents for LB-AC Series

Page 1: ...es correctly This includes properly installing the ground terminal Power on the system only when all cables are properly secured Risk of electric shock do not touch the elements inside the machine whe...

Page 2: ...Wire 3 Phase 4 Wire Power Factor 1 Load Tolerance each step 5 Load Tolerance overall 3 Control Power 110 220 VAC single phase 50 60 Hz Wire Connection Load bank input busbar or terminal block Control...

Page 3: ...ual control or software control user can preset the power then press load master button Loading is according to preset power to avoid load fluctuation during the power changing Control Pattern User ca...

Page 4: ...and query Test data is saved in the software which can be accessed in the testing data history Graphical display View and print real time or historical testing data curves and graphs as follows 1 Grap...

Page 5: ...n off the corresponding protection function to continue working When the control power cable is connected in incorrect phase sequence the 3 phase fan can still work in good condition 3 Appearance 3 1...

Page 6: ...hould be connected to null line N of power supply and load bank And the yellow color cable is connected to phase L1 of power supply and load bank green cable to phase L2 red cable to phase L3 Please m...

Page 7: ...ch on to turn on the machine The unit can be operated by either the control panel or PC 3 Start PC For intelligent control connect to PC and open the supporting data management software on your comput...

Page 8: ...e 5 kW 10 kW switches to get to 15kW Then press the Load Unload switch If you need to change the loading power please press the power setting switches accordingly You may re combine load profile and p...

Page 9: ...nd combined with K M to kW MW Var reactive power symbol unit Var and combined with K M to kVar MVar VA Apparent power symbol Unit VA and K M combination kVA MVA Hz Frequency Symbol Unit Hertz PF Power...

Page 10: ...of three phase current from top to bottom as A B C phase current 3 Display the power frequency power factor and electric energy in the non set state by pressing F1 and button you can view the followin...

Page 11: ...ombination into kvar Mvar 07 Display of three phase apparent power from top to bottom as A B C phase apparent power display units VA and with k M combined into KVA MVA 08 From top to bottom display vo...

Page 12: ...stances occur the fault and the corresponding alarm indicator lights and alarm engage Protection status loading function is locked Identify the reasons for troubleshooting and once resolved release an...

Page 13: ...telligent control with data management software is accomplished by flipping the selector switch to intelligent The recommended configuration to run data management software is Microsoft Windows 98 200...

Page 14: ...se over the lights to view the protection reasons Comment Field Used for information tips of shortcut keys task detail tips and other information 5 3 Communication Settings After the PC is connected t...

Page 15: ...4 Automatic loading You can set the power and duration of each stage sequentially for continuous loading After clicking Power Distribution Active Power column to set load power Power Factor to set pow...

Page 16: ...Real Data to the right of the Real Data window shown the button changes to Stop Save and the program will start saving this real time data of the test After the test is complete click Stop Save to st...

Page 17: ...files Import Records Click Import button then select the recording which you want to import in the dialog box and click OK Export Records Select the record which you want to export click Export confi...

Page 18: ...e will be printed in the report 4 Parameter List Click Set in the toolbar and select Modify Parameters enter the correct data then click OK This page will be printed in the report 5 Print Report Click...

Page 19: ...put away all the parts do not store cables in the sunlight The plug should be covered Using a dust cover for the machine is recommended If used outdoors the load bank should be covered up by a rainpro...

Page 20: ...under test Components heat will disperse moisture to ensure that the device performance is stable and reliable In areas where the air humidity is high no load running on a regular basis is an effecti...

Page 21: ...roblem Check if the cables are connected properly Check if the voltage is in the normal range if voltage is too low power will be low accordingly Remote control has no response Data transmission line...

Reviews: