Connections And Termination
Provisions for combustion and ventilation air must be
in accordance with section, Air For Combustion and
Ventilation, of the National Fuel Gas Code,ANSI 2223.1/
NFPA54, or Sections 8.2, 8.3 or 8.4 of National Gas and
Propane Installation Code, CAN/CGA-B 149.1, or applicable
provisions of the local building code.
Boilers require dedicated direct vent system. All air for
combustion is taken directly from outdoors through
combustion air intake pipe. All
fl
ue products are discharged
to outdoors through vent pipe.
1.
See
Figure 12
thru Figure 14, Pages 24 and 25
for combustion air and vent pipe roof and sidewall
termination. Roof termination is preferred. Combustion
air and vent pipes must terminate together in same
atmospheric pressure zone as shown.
2.
Construction through which vent and air intake pipes
may be installed is maximum 24 inches, minimum ¼”
thickness.
3.
Combustion air and vent pipe
fi
ttings must conform
to American National Standards Institute (ANSI)
standards and American Society for Testing and
Materials (ASTM) standards D1784 (schedule-40
CPVC), D1785 (schedule-40 PVC), D2665 (PVC-DWV),
D2241 (SDR-21 and SDR-26 PVC), D2661 (ABS-DWV),
or F628 (schedule-40 ABS). Pipe cement and primer
must conform to ASTM standards D2564 (PVC) or
D2235 (ABS).
4.
Canada
construct all combustion air and vent pipes
for this unit of ULC S636 listed schedule-40 CPVC,
schedule-40 PVC, PVC-DWV or ABS-DWV pipe and pipe
cement. SDR pipe is not approved in Canada.
• First 3 feet (900mm) of venting must be readily
available for visual inspection.
• Speci
fi
ed primers and glues of certi
fi
ed vent
system must be from single manufacturer, and not
intermixed with other manufacturer’s vent system
parts.
• Components of the certi
fi
ed system must not be
interchanged with other vent systems, or unlisted
pipe and/or
fi
ttings.
NOTICE
Transition from 2” pipe to 3” pipe must be made in
vertical run.
5.
Boiler combustion air and vent piping connections are
sized for 2” pipe. Any pipe size change (to 3”) must be
made outside of boiler casing in vertical run of pipe to
allow for proper drainage of vent condensate. Due to
potential for
fl
ue gas temperatures over 155°F,
fi
rst
fi
ve (5) feet of vent pipe must be CPVC, the remain-
ing vent pipe can be PVC. If any elbows are employed
within the
fi
rst 5 feet of vent, they must be CPVC too.
Two (2) - 30” pieces of 2” CPVC pipe. 2½” piece of 2”
CPVC pipe, a 2” CPVC elbow and 2” CPVC pipe coupling
are furnished with the boiler.
6.
Combustion air and vent piping lengths. Table 5,
Page 23 .
First 5 ft. of vent piping run must be 2”
CPVC:
Length of pipe is counted from boiler jacket (air
intake pipe) or from vent pipe connector(vent pipe).
Termination is not counted toward the “Total Equivalent
Length”.
For elbows, reduce maximum vent length as shown:
• 2” 90° elbow -1 ½ ft. per elbow.
• 3” 90° elbow - 3 ft. per elbow.
Example:
To add two (2) 90° elbows to a 3” pipe for a 75 boiler.
Each elbow is 3 ft. per 90 ° elbow for a total of 6 ft..
(1 elbow @ 3 ft. + 1 elbow @ 3 ft. = 6 equivalent ft. of
pipe)
Total additional pipe is then subtracted from maximum
allowable pipe length to give new maximum length of
106 ft. with two (2), 90° elbows.
“TOTAL EQUIVALENT LENGTH”:
Original 112 ft. max. - 6 equivalent ft. for 2 elbows =
new 106 ft. maximum length.
7.
Pitch combustion air and vent piping back to boiler at
minimum ¼” per ft. (21 mm/m) from intake and vent
terminals so all moisture in combustion air and vent
piping drains to boiler. Pitch pipes continuously with no
sags or low spots where moisture can accumulate and
block
fl
ow of air or
fl
ue gas. Combustion air and vent
pipes must be airtight and watertight.
8.
Consider following when determining appropriate
location for termination of combustion air and vent
piping.
• Position termination where vent vapors will not damage
plants/shrubs or air conditioning equipment.
• Position termination as to not be effected by wind eddy,
air born leaves, snow, or recirculated
fl
ue gases.
• Position termination where it will not be subjected to
potential damage by foreign objects, such as stones,
balls, etc..
• Position termination should where vent vapors are not
objectionable.
• Place vent on wall away from prevailing wind. Locate or
guard vent to prevent accidental contact with people or
pets.
• Terminate vent above normal snowline. Avoid locations
where snow may drift and block vent. Ice or snow may
cause boiler to shut down if vent becomes obstructed.
COMBUSTION AIR AND VENT PIPE
Summary of Contents for Q90-100
Page 2: ...2 DIMENSIONS 2 Figure 1 Boiler Dimensions...
Page 12: ...12 NEAR BOILER PIPING Figure 2 Single Zone Boiler Piping...
Page 14: ...14 Figure 4 Two Zone Boiler Piping With Circulators NEAR BOILER PIPING...
Page 19: ...19 Figure 9 Diaphragm Type Expansion Tank Piping NEAR BOILER PIPING...
Page 20: ...20 Figure 10 Conventional Closed Type Expansion Tank Piping NEAR BOILER PIPING...
Page 24: ...24 Figure 12 Roof Vent Intake Terminations COMBUSTION AIR AND VENT PIPE VENT AIR INTAKE...
Page 32: ...32 Figure 21 Ladder Wiring Diagram ELECTRICAL WIRING...
Page 34: ...34 Figure 23 Ladder Diagram for Figure 22 ELECTRICAL WIRING...
Page 40: ...40 S9381A INTEGRATED BOILER CONTROL OPERATION AND ADJUSTMENTS Table 9 State Code Definitions...
Page 41: ...41 S9381A INTEGRATED BOILER CONTROL OPERATION AND ADJUSTMENTS Figure 26 Sequence of Operation...
Page 48: ...48 TROUBLESHOOTING Table 10 Error Codes...
Page 55: ...NOTES...
Page 56: ...DUNKIRK BOILERS 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com...