6.2 

Cables and connecting lines 

In module design, adopt enclosed connecting boxes with the protective level of IP67 for on-site 

connection to provide environmental influence protection for wires and connections and contacting 

protection  for  non-insulating  electric  parts.  The  connecting  box  has  well  connected  cables  and 

connectors with the protective level of IP67. These designs facilitate parallel connection of modules. 

Each module has two independent wires connecting the connecting box, one is negative pole and 

the other is positive pole. Two modules can be in parallel connection by inserting the positive pole 

at one end of wire of one module into the negative pole of the adjoining module.   

Cables connecting modules shall satisfy the module maximum short circuit current. Adopt the 

special PV system sunlight resistant cables.   

The minimum standards of cables connecting modules are:   

The minimum and maximum outer diameters of the cable are 5 to 7mm2. 

Each module has two standards 90°C sunlight resistant output cables each terminated with plug & 

play connectors. The wire type and gauge of the output cables are 1000V/1500V DC rated PV Wire 

cable and are 4mm

²

  in size. This cable is suitable for applications where wiring is exposed to the direct 

sunlight. We require that all wiring and electrical connections comply with the appropriate National 

Electrical Code. 

When cables are fixed on the bracket, avoid mechanical damage to cables or modules. Do not 

press cables by force. Adopt special designed light resistant wires and clamps to fix cables on the 

bracket. Though cables are light resistant and water proof, it is still necessary to prevent cables from 

direct sun radiation and water immersion.     

The minimum bending radius cables should be 43mm. 

 

6.3 

Connector 

Please  keep  connectors  clean  and  dry.  Make  sure  connector  nuts  are  fastened  before 

connection.  Do  not  connect  connectors  that  are  damp  or  dirty  or  under  other  status.  Protect 

connectors from direct sun radiation and water immersion or fall onto ground or roof.   

Wrong connection may lead to electric arc and electric shock. Please make sure that all 

electric connection is reliable. Make sure all connectors with lock are fully locked.   

The connector type are ZH202

for SUNTER

and    PV-LR4(for Lerri), which only mated with 

the same connector type; 

 

6.4 

Bypass diode 

DualSun module connecting box contains bypass diode which is in parallel connection with the 

cell strands. If heat spot occurs locally with the module, the diode will come into operation to stop 

the main current from flowing through the heat spot cells with the view to restrain module heating 

Summary of Contents for 300M-60-0BBP

Page 1: ...tions in this guide and local regulations Installation of modules requires professional skills and knowledge and is to be carried out by qualified personnel Please read this manual carefully before in...

Page 2: ...lection of tilt angles 7 5 Mechanical installation 7 5 1 Regular requirements 7 5 2 Way of installation 8 6 Electric installation 11 6 1 Electric performance 11 6 2 Cables and connecting lines 13 6 3...

Page 3: ...install modules as per requirements set forth in this manual the quality warranty provided for customers during sales will become invalid In addition suggestions in this manual are to improve safety...

Page 4: ...Regular safety DualSun module is considered to be in compliance with IEC61730 only when the module is mounted in the manner specified by the mounting instructions below When the module is installed o...

Page 5: ...cles and isolate modules from the circuit Working is only allowed in dry conditions by means of dry tools Do not operate when modules are wet unless you wear the proper electric shock protection devic...

Page 6: ...oof Please refer to the IEC61730 1 Clause 12 4 a Fire resistant rating of roof covering Class C b Module installation Angle 22 5 4 Installation conditions 4 1 Installation site and working environment...

Page 7: ...print on the glass due to long time of water ponding which may further affect module appearance and performance 5 Mechanical installation 5 1 Regular requirements Make sure that module installation mo...

Page 8: ...allation as described in this manual load for the test load Note on the basis of IEC61215 2016 installation requirements when computing the corresponding maximum design load need to consider the safet...

Page 9: ...odules on the bracket by metal clamp The following clamps or those clamps recognized by module system installer are recommended Width no less than 40mm Thickness no less than 4mm Material aluminum all...

Page 10: ...e modules have been evaluated by TUV according to IEC61215 for a maximum testing loadof below112 78lb ft2 5400Pa 2400pa design load 3600pa 1600pa 1 5 ML Frame Way of Installation 5400pa 2400pa Mountin...

Page 11: ...testing conditions of irradiance of 1000 W m2 cell temperature of 25 and air mass of AM1 5 Under normal conditions a photovoltaic module is likely to experience conditions that produce more current an...

Page 12: ...nd parallel connection circuit diagram The number of modules in series connection in each strand shall be calculated as per requirements The open circuit voltage value under the expected lowest temper...

Page 13: ...is suitable for applications where wiring is exposed to the direct sunlight We require that all wiring and electrical connections comply with the appropriate National Electrical Code When cables are...

Page 14: ...otect modules from lightning and static electricity damage the module frame shall be grounded The grounding device shall be in full contact with inner side of the aluminum alloy and penetrate the fram...

Page 15: ...mounting holes Mounting holes on modules that are not occupied can be used for installing grounding devices 1 Align grounding clamp to the frame mounting hole Use grounding bolt to go through the gro...

Page 16: ...e degree of influence is determined by transparency of wastes Small amounts of dust will affect sunlight strength and evenness but are not dangerous and power will not be reduced remarkably in general...

Page 17: ...d to carry out a preventive inspection once every 6 month 1 Check connector sealing and cable connection solidness 2 Check whether sealant of the terminal box is cracking with gap Module DualSun 300M...

Reviews: