INSPECTION AND MAINTENANCE 

1. 

Annually

 (also recommended when maintenance is 

performed)

•  Inspect tank, piping, and gaskets for water and 

gas leaks. 

•  All safety devices in the control circuit should be 

cycled on and off to verify they are functioning. 
These include:

–  High limit switch
– Airfl ow proving switch

• 

Tap/softened water humidifi ers only:

–  Low water level probe. Pull out probe plug; fi ll 

valve should energize.

–  Redundant low water level probe

• 

Humidifi ers with the RO/DI water option only:

–  Verify that the fl oat valve is closing off. If the 

fl oat valve will not shut off, there may be 
particulate on the valve seat, or the seat may 
be worn and in need of replacement.

– 

NOTE:

 As long as mineral-free water is used 

in the GTS, no cleaning or fl ushing of the 
humidifi er should be necessary.

2. 

Seasonally

 (or as required, depending on water 

quality) 

Tap/softened water humidifi ers only: 

• Clean 

tank: 

–  Remove cleanout plate, and dispose of any 

loose scale that has collected in the tank. 
Do this before the scale buildup reaches the 
bottom of the heat exchanger. 

–  Inspect the area inside the tank in front of the 

drain valve fi tting, and thoroughly clean all 
scale and mineral buildup from that area.

•  Dismantle and clean drain valve and associated 

piping.

Maintenance 

COOL-DOWN PROCEDURE 

Before performing these maintenance procedures, allow 
the tank to cool down as described here.

NOTE:

  Insulated and uninsulated tanks will have hot 

surfaces.

Verify that there is no call for humidity and that the 
aquastat set point (adjusted using the keypad/display 
Setup screens) is less than room temperature (default 
setting is 4 °C) so the burners do not energize.

• 

GTS models with RO/DI water option and a ball valve 
drain:

1.  Manually open the ball valve, and allow 

approximately half of the water to drain out of the 
tank.
The fl oat valve opens after the water level in the 
tank begins to drop.

2.  Let the fi ll water run until the tank is cooled; then 

shut off the fi eld-installed manual supply water shut-
off valve.

3.  Let the tank drain; then manually close the drain 

valve.

• 

GTS models with tap/softened water and any model 
with end-of-season drain:

1.  From the Main menu, enter the Tank Status 

submenu.

2.  Change mode to Drain, and allow approximately 

half the water to drain out of the tank.

3.  Change the mode back to Auto; the fi ll valve opens 

and the humidifi er cools down.

4.  When the fi ll valve closes, go back into Drain 

mode, and allow the tank to drain completely. The 
humidifi er should be cool enough to work on.

  

WARNING
 Shutdown procedure:

To prevent severe personal injury or death from 
electrical shock, fi re, or explosion, follow this 
shutdown procedure before performing the 
following service or maintenance procedures on this 
humidifi er.
1.   Use Vapor-logic keypad/display, change the 

control mode to Standby. 

2.   Place all power disconnects in OFF position and 

lock in OFF position.

3.   Close fi eld-installed manual supply water shut-off 

valve.

4.   Close gas shut-off valves.

Summary of Contents for GTS-100

Page 1: ...b b b l l l l l l l he he he he he e he e e ere re re re re re re re r Following installation of this steam generating humidifier the installer shall instruct the user in the operation of the steam g...

Page 2: ...ly water piping requirements for all water types 5 Supply water piping Tap softened water 6 RO DI water option 6 Supply water flow rates 6 Supply water guidelines 6 Drain piping 7 Gas piping 8 Combust...

Page 3: ...the European countries listed below Table 1 3 Authorized countries of destination Austria AT Latvia LV Belgium BE Lithuania LT Bulgaria BG Luxembourg LU Cyprus CY Malta MT Czech Republic CZ Netherland...

Page 4: ...ers off and tries to fill the tank If unable to fill the tank within a defined time period an Excessive refill time alarm appears in the Vapor logic Alarm Log The burners remain off until this alarm i...

Page 5: ...off switch if DI RO water option Water level probe Float operated low water cutoff switch if DI RO water option Thermal trip Temperature sensor Tap softened water GTS humidifier shown Steam hose or tu...

Page 6: ...f the structure When such locations cannot be avoided install a suitable drain pan adequately drained under the humidifier The pan must not restrict combustion airflow If located in an insulated space...

Page 7: ...er system while servicing To minimize electrolytic corrosion install insulating unions to make connections between copper and other dissimilar metal fittings such as galvanized steel Humidifier tank m...

Page 8: ...r option If a GTS humidifier with the RO DI water option is supplied with tap softened fill water the float valve assembly will become clogged and particulate will accumulate on the low water cutoff s...

Page 9: ...s adversely affecting their life and performance An open drain with a 25 mm air gap between the drain piping and the drain is required Locate the air gap only in spaces with adequate temperature and a...

Page 10: ...ches when connecting piping to humidifier or controls Provide a drip leg before each humidifier and in the line where low spots cannot be avoided Take off to humidifier should come from top or side of...

Page 11: ...nnection immediately upstream of the gas supply connection to the appliance Use this tap to check pressure with all burners running Leak testing After installation check field piping and humidifier ga...

Page 12: ...xygen for proper combustion openings must be provided to allow outside air to enter the space where the humidifier is located Enclosed spaces such as equipment rooms must be vented for combustion air...

Page 13: ...piping All GTS models have a single point connection to the blower inside the front door See Figure 11 3 When running PVC or CPVC piping for sealed combustion the maximum allowable distance to the out...

Page 14: ...ed according to the provisions of the governing codes Venting Vent connector serving this appliance shall not be connected into any portion of mechanical draft systems operating under positive pressur...

Page 15: ...L VENTING REQUIREMENTS Contact your DriSteem distributor for all horizontal venting parts Ensure that distances from vent terminal to adjacent public walkways buildings and openable windows and buildi...

Page 16: ...e GTS wiring diagrams Control wiring Verify that all control wiring has been completed as specified and required for correct and safe operation of the GTS humidifier Tank Verify that the humidifier ta...

Page 17: ...l down as described here NOTE Insulated and uninsulated tanks will have hot surfaces Verify that there is no call for humidity and that the aquastat set point adjusted using the keypad display Setup s...

Page 18: ...minerals have hardened in the water seal Clean the low water cutout probe Remove the electrical access panel and inspect the probe rod for mineral accumulation The probe rod is located on the top of t...

Page 19: ...ward and physically sound without holes or excessive corrosion Ensure that physical support of the humidifier is sound without sagging cracks or gaps between floor stand or tank flanges Ensure that th...

Page 20: ...ns BURNER MAINTENANCE FREQUENCY Under normal use conditions the burner s should not need cleaning for a minimum of five years However depending on the operating environment the burner s may require pe...