DRISTEEM GTS HUMIDIFIER INSTALLATION AND OPERATION MANUAL

The GTS humidifi er supports both room air and sealed combustion.

•  Do not install the humidifi er in a dusty environment.
•  When the GTS humidifi er is installed in an environment with negative pressure or toxic air, it must have sealed 

combustion.

ROOM AIR COMBUSTION 

  

WARNING

 

Air for combustion:

Air for combustion must not be contaminated by halogen compounds, which include fl uoride, chloride, bromide, 
and iodide. These elements are found in aerosol sprays, detergents, bleaches, cleaning solvents, salts, air 
fresheners, and other household products.

Failure to follow these instructions could cause severe bodily injury or death.

•  All fuel-burning equipment must be supplied with air for combustion. Suffi cient air must be provided to ensure there 

is not a negative pressure in the equipment room or space. 

•  Do not block or obstruct air openings on the appliance, spaces around the appliance, or air openings to the 

appliance area.

•  Do not block the fl ow of combustion and ventilation air. To provide necessary oxygen for proper combustion, 

openings must be provided to allow outside air to enter the space where the humidifi er is located. Enclosed spaces, 
such as equipment rooms, must be vented for combustion air. The size of air openings must be based on all gas-
burning equipment installed in the space. Table 10-1 outlines four types of locations, and the requirements of each. 

 Combustion and ventilation air 

Table 10-1:
Location of humidifier and required air openings

Location description

Required air opening

Confi ned space with all air from inside the building; conventional frame, brick or 
stone construction with normal infi ltration

Note:

 this location rarely provides enough air for higher-capacity humidifi ers.

Two openings, 6.5 cm

2

 per opening per 293 W input

The minimum free area of all openings combined is 645 cm

2

.

Confi ned space with all air from outside the building through air ducts

Two openings, 2 ducts, 6.5 cm

2

 per opening per 586 W 

input*

Confi ned space with all air from outside the building from through-wall openings 
only (no ducts)

Two openings, 6.5 cm

2

 per opening per 1172 W input*

Unconfi ned space with all air from outside the building

Same as confi ned space; all air from outside the building

* The minimum dimension of any opening is 76 mm × 76 mm.

Summary of Contents for GTS-100

Page 1: ...b b b l l l l l l l he he he he he e he e e ere re re re re re re re r Following installation of this steam generating humidifier the installer shall instruct the user in the operation of the steam g...

Page 2: ...ly water piping requirements for all water types 5 Supply water piping Tap softened water 6 RO DI water option 6 Supply water flow rates 6 Supply water guidelines 6 Drain piping 7 Gas piping 8 Combust...

Page 3: ...the European countries listed below Table 1 3 Authorized countries of destination Austria AT Latvia LV Belgium BE Lithuania LT Bulgaria BG Luxembourg LU Cyprus CY Malta MT Czech Republic CZ Netherland...

Page 4: ...ers off and tries to fill the tank If unable to fill the tank within a defined time period an Excessive refill time alarm appears in the Vapor logic Alarm Log The burners remain off until this alarm i...

Page 5: ...off switch if DI RO water option Water level probe Float operated low water cutoff switch if DI RO water option Thermal trip Temperature sensor Tap softened water GTS humidifier shown Steam hose or tu...

Page 6: ...f the structure When such locations cannot be avoided install a suitable drain pan adequately drained under the humidifier The pan must not restrict combustion airflow If located in an insulated space...

Page 7: ...er system while servicing To minimize electrolytic corrosion install insulating unions to make connections between copper and other dissimilar metal fittings such as galvanized steel Humidifier tank m...

Page 8: ...r option If a GTS humidifier with the RO DI water option is supplied with tap softened fill water the float valve assembly will become clogged and particulate will accumulate on the low water cutoff s...

Page 9: ...s adversely affecting their life and performance An open drain with a 25 mm air gap between the drain piping and the drain is required Locate the air gap only in spaces with adequate temperature and a...

Page 10: ...ches when connecting piping to humidifier or controls Provide a drip leg before each humidifier and in the line where low spots cannot be avoided Take off to humidifier should come from top or side of...

Page 11: ...nnection immediately upstream of the gas supply connection to the appliance Use this tap to check pressure with all burners running Leak testing After installation check field piping and humidifier ga...

Page 12: ...xygen for proper combustion openings must be provided to allow outside air to enter the space where the humidifier is located Enclosed spaces such as equipment rooms must be vented for combustion air...

Page 13: ...piping All GTS models have a single point connection to the blower inside the front door See Figure 11 3 When running PVC or CPVC piping for sealed combustion the maximum allowable distance to the out...

Page 14: ...ed according to the provisions of the governing codes Venting Vent connector serving this appliance shall not be connected into any portion of mechanical draft systems operating under positive pressur...

Page 15: ...L VENTING REQUIREMENTS Contact your DriSteem distributor for all horizontal venting parts Ensure that distances from vent terminal to adjacent public walkways buildings and openable windows and buildi...

Page 16: ...e GTS wiring diagrams Control wiring Verify that all control wiring has been completed as specified and required for correct and safe operation of the GTS humidifier Tank Verify that the humidifier ta...

Page 17: ...l down as described here NOTE Insulated and uninsulated tanks will have hot surfaces Verify that there is no call for humidity and that the aquastat set point adjusted using the keypad display Setup s...

Page 18: ...minerals have hardened in the water seal Clean the low water cutout probe Remove the electrical access panel and inspect the probe rod for mineral accumulation The probe rod is located on the top of t...

Page 19: ...ward and physically sound without holes or excessive corrosion Ensure that physical support of the humidifier is sound without sagging cracks or gaps between floor stand or tank flanges Ensure that th...

Page 20: ...ns BURNER MAINTENANCE FREQUENCY Under normal use conditions the burner s should not need cleaning for a minimum of five years However depending on the operating environment the burner s may require pe...

Page 21: ...less than 40 ppm low single digits is the norm CO2 from 8 to 10 preferably 9 O2 between 4 and 7 Flue Temperature less than 204 C plus room temperature Burner efficiency greater than 80 Orange color f...

Page 22: ...act negligence strict liability in tort or any other legal theory even if DriSteem has notice of the possibility of such damages By purchasing DriSteem s products the purchaser agrees to the terms and...

Reviews: