Schedule a Consistency Check
A Consistency Check task can be scheduled for later in the day or week. A Consistency Check task can be
scheduled to run each week or each month.
NOTE:
Schedule only one Consistency Check event on an array. This means that if a monthly check has been
scheduled and a weekly check is desired, delete the monthly event and schedule the new event.
The following scheduling options are available for a Consistency Check.
Schedule a Consistency Check for later
1.
Click the array on which to run the Consistency Check.
2.
On the Array drop-down menu or by selecting an array and right-clicking, select
Check Consistency
.
3.
Click
Schedule
.
4.
At the Check Consistency dialog box, select the frequency, day, and time.
5.
Click
Confirm
.
Delete a scheduled Consistency Check
1.
Click the array on which to delete the Consistency Check.
2.
From the Array drop-down menu or by selecting an array and right-clicking, select
Check Consistency
.
3.
Click
Schedule
.
4.
At the Consistency Check dialog box, click
Cancel
.
Table 39
Consistency Check Options
Option
Description
One Time Only
Schedule the Consistency Check for the current day (“Today”) or up to seven
days in the future.
Weekly
Events can be scheduled weekly. After it is selected, a Consistency Check runs
on the specified array at the same time each week.
Monthly
Events can be scheduled to run once per month to run on the specified array at
a specified time.
Summary of Contents for RAIDCore
Page 1: ...P N 83 00004638 12 Revision A December 2009 RAIDCore User Manual ...
Page 8: ...RAIDCore User Manual 6 ...
Page 10: ...8 Figures ...
Page 16: ...14 Chapter 1 Safety Precautions ...
Page 106: ...104 Chapter 6 RAIDConsole Graphical User Interface GUI ...
Page 120: ...118 Appendix A Software License EULA ...
Page 130: ...128 Glossary ...