DIVERSIFIED METAL FABRICATORS, INC.
RW-1016
© 2017 DMF, Inc. All Rights Reserved.
4-25
4.10
INSTALLATION REVIEW
4.10.1
General Inspection
Check that all fasteners are tight.
Verify lug nut torque.
Check tire inflation pressures (cold).
Verify final weld out has been performed as detailed in section 4.8.
Touch up paint welded or drilled areas as necessary.
Check that all hoses and wire are routed properly and protected from abrasion, heat,
and pinch points.
Verify that all electrical terminations are insulated and protected.
Verify that the hydraulic reservoir is full and labeled.
Verify that all bodywork is replaced and secure.
4.10.2
Railgear Function Test
Verify that the Railgear does not operate with the power switch in the off position.
Verify the power indication on the power switch in the cab.
Test the wireless railgear controls, and any hardwired controls.
Verify the pin-offs work in both the rail and highway positions (if equipped).
Follow Section 2.4 to verify emergency pump function.
Load test vehicle to GVWR and verify Railgear function.
4.10.3
Road Test
Before road testing: inspect steering stops, wheel and tires. Verify that the lug nuts
have been properly torqued.
In a parking lot or open area, verify that the steering stops prevent the tire or rim from
contacting the frame, suspension or other items.
Inspect brake lines and ABS sensor lines to verify clearance from rim.
Check for any rattles and vibration.
Verify speedometer calibration by timing a distance, GPS or from another vehicle. (This
may not be necessary for every install.)
Verify that no TPMS malfunction lights on the dash are illuminated.
4.10.4
Before Customer Delivery
Verify that the wireless control unit is safely stowed and easily accessible.
Verify that the emergency pump handle is safely stowed.
Include this manual in the vehicle for operator reference.
Include this checklist and a completed alignment sheet in the vehicle for the customer’s
records.
Summary of Contents for RW-1016
Page 22: ......
Page 30: ......
Page 46: ......
Page 47: ......
Page 48: ......
Page 54: ......
Page 55: ......
Page 56: ......
Page 59: ......
Page 60: ......
Page 97: ...2017 DMF Inc All Rights Reserved Page 4 of 4 Page left intentionally blank...
Page 102: ...2017 DMF Inc All Rights Reserved Page 5 of 5 Page left intentionally blank...
Page 107: ...2017 DMF Inc All Rights Reserved Page 5 of 5 Page left intentionally blank...
Page 110: ...DIVERSIFIED METAL FABRICATORS INC RW 1016 2017 DMF Inc All Rights Reserved...