67
EN
Operating the PV inverter
nOTE
► If selecting
Germany or Italy
as the country, it could be necessary to
adjust active and reactive power settings (Information for the settings
will come from the local grid operator).
► If needed please call the local support hotline for assistance in setting
up Germany MVD/LVD or Italy CEI 0-21/A70 grid settings.
4. Start up the inverter:
–
After finishing the basic settings, turn on DC switches (including the DC switch in in-
verter), inverter will do some self-tests and start a countdown if there is no problem.
–
When operating, check all information on the display is correct (ex. Input voltage, current
and power; output voltage, current, power and frequency)
When solar irradiation is sufficient, the device will operate automatically, after the self-auto test is
completed successfully (about 2 minutes on the first startup of a day). Please refer to Figure 7.2
showing the LCD Display and Control Panel details. The display includes a 5“ graphic LCD with
320x240 dots of resolution and a LED indicator showing inverter status. There are green and red
colored LED indicator lights to represent various inverter states of operation. Please refer to Table
7-1 for more detail on the LED indicator.
ESC: ESC MENU
DOWN: MOVE DOWN
UP: MOVE UP
ENTER: ENTER MENU OR CONFIRM
LED Indicator (GRN/RED)
LCD Display
Figure 7.2.: LCD Display and Control Panel