Installation Manual
Festoon Systems for I-Beams
Program 0314
Commissioning checklist
MAL0300-0001-EN
www.conductix.com
translated document
page 37 of 56
Checks with the system at a standstill
OK
Not OK
A12
Welded joints of the track beam are ground smooth on all roller surfaces.
A13
The corrosion protection is undamaged and intact.
Inspections on running systems
with 10% running speed:
Movement forwards from cable trolley storage/termination fitting end in direction of towing end until the cable train is fully extended.
Movement backwards from towing end in the direction of cable trolley storage/termination fitting end until end position is reached.
B01
Horizontal alignment gap between the cable trolley and the crane construction is wide enough that no collision can take place with cable trolleys or their
components.
B02
Check of the loop lengths at the maximum pulled out festoon system corresponds to the project-specific technical documentation.
Documentation
F01
Project-specific documentation is available and complete at the customer's facility, along with technical data, system diagrams, cable layout suggestion, and
round / flat cable terminal layouts.