![Delachaux Conductix-Wampfler 0314 Series Installation Manual Download Page 36](http://html1.mh-extra.com/html/delachaux/conductix-wampfler-0314-series/conductix-wampfler-0314-series_installation-manual_2465764036.webp)
Installation Manual
Festoon Systems for I-Beams
Program 0314
Commissioning checklist
MAL0300-0001-EN
www.conductix.com
translated document
page 36 of 56
Checks with the system at a standstill
OK
Not OK
A01
The track of the carriage corresponds to the project-specific technical documentation.
A02
The storage length of the festoon system corresponds to the project-specific technical documentation.
A03
All bolts used are of sufficient length and are protected. The projecting ends of the screws are visible (at least 2 thread projection).
A04
Cables are to be arranged according to specifications in the cable arrangement recommendation (see project-specific technical documentation).
A05
Loop lengths of the cables correspond to the specifications of the project-specific technical documentation. The permissible
length deviation is
50 mm
.
Actual
________
A06
Cables are arranged free of twists
A07
Cables show no damage caused by transport or assembly.
A08
The cables are mounted on the supports in such a way that the cable trolleys run horizontally on the track profile (balance of the cables on the right and left
supports).
Cable holders are to be firmly tightened so that cables cannot be pulled out manually, but still with enough play that the cables are also not crushed.
A09
Cable ends (installation lengths) are arranged with sufficient strain relief and the right length to the end or towing side.
A10
Check steel structure for collision-free travel of the festoon system. No trapping and hooking of lines possible.
A11
Joints of the track carrier have no height and side offset