Test Operation
SiE-05C
272
Test Operation PLUS Series
1. Test Operation
1.1
Procedure and Outline
The operation sequence is the most important thing for test operation. Follow the following outline.
1.1.1
Check The Following Before Turning Power On.
1.1.2
Turn Power On.
Refer to Setting Modes on P278
Mistaken power wiring, loose screws
Mistaken control transmission wiring, loose screws
Piping size, presence of thermal insulation
Measurement of main power circuit insulation
Outdoor No. switch of constant speed type outdoor unit (SS2)
Addition or replenishment of refrigerant as needed
Fully close respective stop valves on liquid,
gas and pressure equalizing sides of function unit,
inverter type and constant speed type units.
Use a 500V megar-tester.
Be sure to record addition or replenishment.
(VF128)
Turn on outdoor unit power.
Set various selectable modes on the function unit PC board.
Turn on indoor unit power.
Be sure to turn the power on 6 hours before
starting operation in order to supply electricity
to the crankcase heater.
For field settings, see setting modes.
(VF129)