5 Commissioning

Installation manual

14

RZAG71~Y1

Sky Air Alpha-series

4P485927-1C – 2019.04

f

b

a

e

d

c

a

Gas pipe

b

Gas pipe insulation

c

Interconnection cable

d

Liquid pipe

e

Liquid pipe insulation

f

Finishing tape

2

Install the service cover.

4.6.2

To check the insulation resistance of the
compressor

NOTICE

If,  after  installation,  refrigerant  accumulates  in  the
compressor,  the  insulation  resistance  over  the  poles  can
drop,  but  if  it  is  at  least  1  MΩ,  then  the  unit  will  not  break
down.

▪ Use a 500 V mega-tester when measuring insulation.

▪ Do not use a mega-tester for low-voltage circuits.

1

Measure the insulation resistance over the poles.

If

Then

≥1 MΩ

Insulation resistance is OK. This procedure
is finished.

<1 MΩ

Insulation resistance is not OK. Go to the
next step.

2

Turn ON the power and leave it on for 6 hours.

Result: 

The  compressor  will  heat  up  and  evaporate  any

refrigerant in the compressor.

3

Measure the insulation resistance again.

5

Commissioning

Please  provide  the  eco  design  data  according  to  (EU)2016/2281  to
the customer. This data can be found in the installer reference guide
or via the Daikin website.

NOTICE

NEVER  operate  the  unit  without  thermistors  and/or
pressure  sensors/switches.  Burning  of  the  compressor
might result.

5.1

Checklist before commissioning

After the installation of the unit, first check the following items. Once
all  below  checks  are  fulfilled,  the  unit  MUST  be  closed,  ONLY  then
can the unit be powered up.

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

In case a wireless user interface is used: The 

indoor unit

decoration panel

 with infrared receiver is installed.

The 

outdoor unit

 is properly mounted.

The following 

field wiring

 has been carried out according

to this document and the applicable legislation:

▪ Between the local supply panel and the outdoor unit

▪ Between the outdoor unit and the indoor unit (master)

▪ Between the indoor units

There are NO 

missing phases

 or 

reversed phases

.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed according to this document, and have NOT been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

5.2

To perform a test run

This task is only applicable when using the BRC1E52 user interface.

▪ When  using  BRC1E51,  see  the  installation  manual  of  the  user

interface.

▪ When using BRC1D, see the service manual of the user interface.

NOTICE

Do not interrupt the test run.

INFORMATION

Backlight.

  To  perform  an  ON/OFF  action  on  the  user

interface,  the  backlight  does  not  need  to  be  lit.  For  any
other  action,  it  needs  to  be  lit  first.  The  backlight  is  lit  for
±30 seconds when you press a button.

1

Perform introductory steps.

#

Action

1

Open the liquid stop valve and gas stop valve by
removing the cap and turning counterclockwise with a
hex wrench until it stops.

2

Close the service cover to prevent electric shocks.

3

Turn ON power for at least 6 hours before starting
operation to protect the compressor.

4

On the user interface, set the unit to cooling operation
mode.

2

Start the test run.

#

Action

Result

1

Go to the home menu.

Cool

Set to

28

°C

2

Press at least 4 seconds.

The Service Settings menu
is displayed.

Summary of Contents for SkyAir RZAG125M7V1B

Page 1: ...Installation manual Sky Air Alpha series English Installation manual Sky Air Alpha series RZAG71M7V1B RZAG100M7V1B RZAG125M7V1B RZAG140M7V1B RZAG71M7Y1B RZAG100M7Y1B RZAG125M7Y1B RZAG140M7Y1B...

Page 2: ...1000 1000 500 HD HU HU a b 100 100 c d e eB eD A B C D E HB HD A B C 200 300 1000 A B C E 200 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 HD HU 250 1500 HU HD HU 300 1500 B D E HB H...

Page 3: ...onforme altera o em 10 11 12 13 14 15 16 17 Direktiver med senere ndringer Direktiv med f retagna ndringar Direktiver med foretatte endringer Direktiivej sellaisina kuin ne ovat muutettuina v platn m...

Page 4: ...PS vastaava kyll stysl mp tila M C Kylm aine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maxim ln p pustn tlak PS K bar Minim ln maxim ln p pustn teplo...

Page 5: ...2 To check the insulation resistance of the compressor 14 5 Commissioning 14 5 1 Checklist before commissioning 14 5 2 To perform a test run 14 5 3 Error codes when performing a test run 15 5 4 Dedica...

Page 6: ...d supply as follows mm 150 6 2 0 350 3 4 5 3 5 5 4 M12 a a Make sure not to cover the drain holes of the bottom plate of the unit INFORMATION The recommended height of the upper protruding part of the...

Page 7: ...b c d INFORMATION b b b b a a Remove the knockout hole a in the bottom plate or cover plate by tapping on the attachment points with a flat head screwdriver and a hammer Optionally cut out the slits...

Page 8: ...flare nut and the copper flare 1 Charge the system with nitrogen gas up to a gauge pressure of at least 200 kPa 2 bar It is recommended to pressurize to 3000 kPa 30 bar in order to detect small leaks...

Page 9: ...efrigerant circuit so the vacuuming process or recharge of refrigerant can be done properly Before vacuum drying or recharging activate field setting vacuum mode After finishing vacuum drying or recha...

Page 10: ...of twin triple and double twin 1 Determine G1 and G2 G1 m Total length of x liquid piping x 9 5 mm standard x 12 7 mm size up G2 m Total length of 6 4 mm liquid piping 2 Determine R1 and R2 If Then G...

Page 11: ...When 2 28 is reached press the BS3 button once 4 Change the setting to 1 by pressing the BS2 button once 5 Push the BS3 button once 6 When the display is not blinking anymore press the BS3 button aga...

Page 12: ...onnected to public low voltage systems with input current 16 A and 75 A per phase RZAG71 140M7Y1B Equipment complying with EN IEC 61000 3 2 European International Technical Standard setting the limits...

Page 13: ...e of the 3 possibilities a b a b a b 2 3 1 a Power supply cable b Interconnection cable Connecting to the frame When cables are routed from the unit a protection sleeve for the conduits PG insertions...

Page 14: ...g field wiring has been carried out according to this document and the applicable legislation Between the local supply panel and the outdoor unit Between the outdoor unit and the indoor unit master Be...

Page 15: ...oor unit and user interface The fuse on the outdoor unit PCB has blown out E3 E4 or L8 The stop valves are closed The air inlet or air outlet is blocked E7 There is a missing phase in case of three ph...

Page 16: ...nimum service space between the unit and obstacles A B C D and E eB Maximum distance between the unit and the edge of obstacle E in the direction of obstacle B eD Maximum distance between the unit and...

Page 17: ...e Outdoor Outdoor Indoor Indoor Upper Upper Lower Lower Fan Fan ON ON OFF OFF 2 Layout English Translation Layout Layout Front Front Back Back Position of compressor terminal Position of compressor te...

Page 18: ...t breaker 30 mA Q1E Overload protection R1 R8 A1P Y1 only Resistor R1T Thermistor air R2T Thermistor discharge R3T Thermistor suction R4T Thermistor heat exchanger R5T Thermistor heat exchanger middle...

Page 19: ......

Page 20: ...4P485927 1C 2019 04 Copyright 2017 Daikin 4P485927 1 C 00000007...

Reviews: