Be sure to perform a test run.

Be sure to fully open the liquid-side and gas-side stop valves. If
you operate the unit with stop valves closed, the compressor will
break down.

Be sure to execute the first test run of the installation in cooling
mode operation.

Never leave the unit unattended with an open front panel during
test run.

Test run

1

Be sure to turn power on at least 6 hours before starting
operation in order to protect the compressor.

2

Make sure the liquid and gas stop valves are open.

3

Be sure to close the frontside panel before operation, as not
doing so can cause electric shock.

4

Be sure to set the unit to cooling operation mode.

5

Press the inspection/test operation button of the remote
controller 4 times (2 times in case of a wireless remote
controller) to go into the test run mode.

6

Press the ON/OFF button within 10 seconds to start the test run
and check the operation status for about 6 minutes. The
refrigerant pressure may not rise immediately, even if the stop
valve is opened after an air purge is performed using a vacuum
pump. This is because the indoor unit refrigerant piping is closed
off with electric valves inside. This will not create any problems
during operation.

7

Push the air flow direction adjust button and check if the unit is
responding to the new air flow direction position.

8

Press the inspection/test operation button of the remote
controller 2 times to go into check mode and to make sure that
the malfunction code displays "

00

"  (=normal). In case the

malfunction code does not display "

00

", refer to 

"Failure

diagnosis at the moment of first installation" on page 14

.

9

If the inspection/test operation button is pressed 4 times during
a test run, the unit returns to normal operation.

10

Check all functions according to the operation manual.

Precautions regarding test-runs

1

In order to detect stop valves failing to open, operation of the
unit is compulsorily performed in cooling for 2-3 minutes during
the first test run, even if the remote controller was set to heating
operation. In this case, the remote controller will have kept
displaying the heating symbol all the time and the unit will switch
to heating operation automatically after elapse of that time.

2

In case you cannot operate the unit in test run mode for any
unusual reason, refer to 

"Failure diagnosis at the moment of first

installation" on page 14

.

3

In case you cannot operate the unit in test run mode, the unit
usually returns to its normal state after 30 minutes.

4

In case of a wireless remote controller, execute the test run only
after having installed the indoor unit decoration panel with infra-
red receiver first.

5

In case the panels of indoor units are not yet installed to the
indoor units, make sure to shut off the power supply after
finishing the complete test run.

6

A complete test run surely includes shutting off power after
having performed a normal operation stop on the remote
controller. Do not stop operation by turning circuit breakers off.

Failure diagnosis at the moment of first installation

In case nothing is displayed on the remote controller (the current set
temperature does not display), check for any of the following
abnormalities before you can diagnose possible malfunction codes.

Disconnection or wiring error (between power supply and
outdoor unit, between outdoor unit and indoor units, between
indoor unit and remote controller).

The fuse on the outdoor unit PCB may have run out.

If the remote controller shows "

E3

", "

E4

or "

L8

" as an error code,

there is a possibility that either the stop valves are closed, or that
air inlet or air outlet are blocked.

If the error code "

U2

" is displayed on the remote controller, check

for voltage imbalance.

If the error code "

U4

"  or  "

UF

"  is displayed on the remote

controller, check the inter-unit branch wiring connection.

If the error code 

"L4"

 is displayed on the remote controller, it is

possible that air inlet or air outlet are blocked.

The reversed phase protection detector of this product only
works during the initialisation stage after a power reset.
The reversed phase protection detector is designed to stop the
product in case of an abnormality when the product is started
up.

When the reversed phase protection circuit forced the unit to
stop, check if all phases are existing. If this is the case, shut
off the power supply to the unit and replace two of three
phases. Turn on power again and start the unit.

Reversed phase detection is not performed while the product
is operating.

In case of possible reversal of phases after a momentary
black out of power and the power goes on and off while the
product is operating, install a reversed phase protection
circuit on site. Such situation is not unimaginable when using
generators. Running the product in reversed phase can
break the compressor and other parts.

For a missing phase in case of W1 units, "

E7

"  or  "

U2

"  will be

displayed on the remote controller of the indoor unit.
Operation will be impossible with either one of these
phenomena. If this happens, turn off the power, re-check the
wiring and switch the position of two of the three electrical wires.
(If operation is not possible, do not under any circumstances
force the electromagnetic contactor on.)

D

ISPOSAL

 

REQUIREMENTS

Dismantling of the unit, treatment of the refrigerant, of oil and of other
parts must be done in accordance with relevant local and national
legislation.

 Opening direction

A

Liquid side

B

Gas side

Remove the cap and turn 
counterclockwise with a 
hex wrench until it stops

A

B

Summary of Contents for RZQ71D7V1B

Page 1: ...INSTALLATION MANUAL RZQ71D7V1B RZQ71D2V1B RZQ100D7V1B RZQ125D7V1B RZQ140D7V1B RZQ100B8W1B RZQ125B8W1B RZQ140B8W1B Split System air conditioners...

Page 2: ...5 9 7 6 6 8 3 3 1 3 2 4 5 A B A E B C D H H1 L1 H1 H2 L3 L1 L2 H1 H2 L4 L1 L3 L2 H1 H2 L7 L1 L6 L5 L4 L3 L2 A A B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 A A B1 B1 B1 B1 B1 B1 B2...

Page 3: ...bestemmelsene i 13 noudattaen m r yksi 14 za dodr en ustanoven p edpisu 15 prema odredbama 16 k veti a z 17 zgodnie z postanowieniami Dyrektyw 18 n urma prevederilor 19 ob upo tevanju dolo b 20 vasta...

Page 4: ...ns or earthquakes Improper installation work may result in accidents due to fall of equipment Make certain that all electrical work is carried out by qualified personnel according to the local laws an...

Page 5: ...salt such as that near the ocean Where voltage fluctuates a lot such as that in factories In vehicles or vessels Where acidic or alkaline vapour is present Provide a logbook In accordance with the re...

Page 6: ...wind blows continuously on the face of the unit the fan can start rotating very fast until it breaks Refer to the figures for installation of this unit in a place where the wind direction can be fores...

Page 7: ...water may splash on people provide the drain piping using a drain socket optional Make sure the drain works properly INSTALLATION SERVICING SPACE The numerical figures used in here represent the dime...

Page 8: ...and international codes In Europe EN378 is the applicable standard that shall be used To persons in charge of piping work Be sure to open the stop valve after piping installing and vacuming is comple...

Page 9: ...te the room thoroughly right away Use R410A only when adding refrigerant Installation tools Make sure to use installation tools gauge manifold charge hose etc that are exclusively used for R410A insta...

Page 10: ...e effects If the indoor or outdoor units were disconnected from the piping for a long period of time water or dirt might have gotten into the piping If copper piping is corroded Flares should not be r...

Page 11: ...ions when connecting field piping and regarding insulation Be careful not to let the indoor and outdoor branch piping come into contact with the compressor terminal cover If the liquid side piping ins...

Page 12: ...y closed before leak test or vacuuming Set up for vacuuming and leak test see figure 8 Procedure for leak test Leak test must satisfy EN378 2 1 Evacuate the pipes and check vacuum 1 No pressure increa...

Page 13: ...amount is R1 R2 1 G1 total length of 9 5 mm liquid piping G2 total length of 6 4 mm liquid piping 2 a G1 30 m calculate length over 30 m G1 30 m Based on this length decide R1 R2 in the table b G1 30...

Page 14: ...ove and use the table below G1 total length of 12 7 mm liquid piping Length exceeding Chargeless length Model Liquid piping 0 5 m 5 10 m 10 15 m 15 20 m RZQ71 Main 12 7 0 5 1 0 RZQ100 140 Main 1 5 2 0...

Page 15: ...apacitor abnormal heating accident due to high frequency waves Therefore never install a phase advancing capacitor Secure the wiring in the order shown below 1 Secure the ground wire to the stop valve...

Page 16: ...e maximum values see electrical data of combination with indoor units for exact values 18 9 27 6 28 8 17 1 18 3 Recommended field fuse A 20 32 20 Wire type b b Only in protected pipes use H07RN F when...

Page 17: ...it decoration panel with infra red receiver first 5 In case the panels of indoor units are not yet installed to the indoor units make sure to shut off the power supply after finishing the complete tes...

Page 18: ...charge for V1 models only R3T Thermistor discharge pipe for W1 models only R3T Thermistor suction pipe for V1 models only R4T Thermistor suction pipe for W1 models only R4T Thermistor coil for V1 mode...

Page 19: ...NOTES NOTES...

Page 20: ...4PW48323 1B Copyright Daikin...

Reviews: