7 Commissioning

Installation and operation manual

26

RWEYQ8~RWEYQ8~14T9Y1B

VRV IV water-cooled system air conditioner

4P452190-1A – 2017.04

[2‑50]

Brine type setting.

By changing this setting, you can extend the operation range at the
brine side of the unit.

▪ Normal operation range at brine side (default): for use with water

as heat source medium.

▪ Extended operation range at brine side (default): for use with brine

as heat source medium.

NOTICE

By changing this setting to extended operation type, glycol
(40%)  must  be  used  as  heat  source  medium  to  avoid
freeze  up  of  the  brine  circuit  or  unit  itself  (cf.  operation
range). Do not use water in this case!

[2‑50]

Description

0 (default)

No brine: water. Extended range impossible.

3

Use brine: glycol (40%). Extended range
possible.

[2‑73]

Zero energy dissipation control setting.

[2‑73]

Description

0 (default)

OFF

1

ON (with priority on cooling capacity)

2

ON (with priority on zero energy dissipation)

Zero energy dissipation control can be OFF if the mechanical room
is  already  equipped  with  a  ventilation  system  or  air  conditioning
system for other facilities.

[2‑74]

Zero energy dissipation setting temperature.

If  the  unit  internal  temperature  is  higher  than  the  zero  energy
dissipation  setting  temperature,  the  zero  energy  dissipation  control
will start and cool down the unit.

[2‑74]

Description

0

25

1

27

2

29

3 (default)

31

4

33

5

35

6

37

7

39

6.1.9

To connect the PC configurator to the
outdoor unit

X27A

a

b

c

2

3

4

5

H J

ST

X27A

A1P

a

PC

b

Cable (EKPCCAB)

c

Outdoor unit main PCB

7

Commissioning

After installation and once the field settings are defined, the installer
is  obliged  to  verify  correct  operation.  Therefore  a  test  run  must  be
performed according to the procedures described below.

7.1

Precautions when commissioning

CAUTION

Do not perform the test operation while working on the
indoor units.

When  performing  the  test  operation,  not  only  the  outdoor
unit,  but  the  connected  indoor  unit  will  operate  as  well.
Working on an indoor unit while performing a test operation
is dangerous.

NOTICE

Be  sure  to  turn  on  the  power  6  hours  before  operation  in
order  to  have  power  running  to  the  crankcase  heater  and
to protect the compressor.

During test operation, the outdoor unit and the indoor units will start
up.  Make  sure  that  the  preparations  of  all  indoor  units  are  finished
(field  piping,  electrical  wiring,  air  purge,  ...).  See  installation  manual
of the indoor units for details.

7.2

Checklist before commissioning

After the installation of the unit, first check the following items. Once
all below checks are fulfilled, the unit must be closed, only then can
the unit be powered up.

You  read  the  complete  installation  and  operation
instructions,  as  described  in  the 

installer  and  user

reference guide

.

Installation

Check that the unit is properly installed, to avoid abnormal
noises and vibrations when starting up the unit.

Field wiring

Be  sure  that  the  field  wiring  has  been  carried  out
according  to  the  instructions  described  in  the  chapter

"5.8  Connecting  the  electrical  wiring"  on  page  20

,

according  to  the  wiring  diagrams  and  according  to  the
applicable legislation.

Power supply voltage

Check the power supply voltage on the local supply panel.
The  voltage  must  correspond  to  the  voltage  on  the
identification label of the unit.

Earth wiring

Be  sure  that  the  earth  wires  have  been  connected
properly and that the earth terminals are tightened.

Insulation test of the main power circuit

Using  a  megatester  for  500  V,  check  that  the  insulation
resistance  of  2  MΩ  or  more  is  attained  by  applying  a
voltage of 500 V DC between power terminals and earth.
Never use the megatester for the transmission wiring.

Fuses, circuit breakers, or protection devices

Check  that  the  fuses,  circuit  breakers,  or  the  locally
installed  protection  devices  are  of  the  size  and  type
specified 

in 

the 

chapter 

"4.4.1 

Safety 

device

requirements" on page 12

. Be sure that neither a fuse nor

a protection device has been bypassed.

Summary of Contents for RWEYQ10T9Y1B

Page 1: ...lation and operation manual VRV IV water cooled system air conditioner English Installation and operation manual VRV IV water cooled system air conditioner RWEYQ8T9Y1B RWEYQ10T9Y1B RWEYQ12T9Y1B RWEYQ1...

Page 2: ...8 19 20 21 22 23 24 25 Directivelor cu amendamentele respective Direktive z vsemi spremembami Direktiivid koos muudatustega Direktyvose su papildymais Direkt v s un to papildin jumos Smernice v platno...

Page 3: ...S vastaava kyll stysl mp tila M C Kylm aine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maxim ln p pustn tlak PS K bar Minim ln maxim ln p pustn teplot...

Page 4: ...19 5 7 Connecting the water piping 20 5 7 1 About connecting the water piping 20 5 7 2 To connect the water piping 20 5 7 3 To fill the water circuit 20 5 7 4 To insulate the water piping 20 5 8 Conn...

Page 5: ...ed installers end users Documentation set This document is part of a documentation set The complete set consists of General safety precautions Safety instructions that you must read before installing...

Page 6: ...it This installation manual concerns the VRV IV water cooled system air conditioner The unit is full inverter driven and can be used for cooling heat pump and heat recovery applications Model line up...

Page 7: ...er 4 Preparation 4 1 Preparing installation site 4 1 1 Installation site requirements of the outdoor unit Mind the spacing guidelines See the Technical data chapter CAUTION Appliance not accessible to...

Page 8: ...termine the proper size using the following tables and reference figure only for indication In case of heat pump mode A B B B C D F G E x y b a 3 1 2 4 5 1 2 VRV DX indoor unit 3 BP box 4 5 RA DX indo...

Page 9: ...meter size mm 18 22 15 9 19 1 24 26 34 19 1 22 2 36 42 F Piping between refrigerant branch kit and BP unit Heat pump mode in case of single outdoor unit Pipe size for direct connection on BP unit must...

Page 10: ...b a a To indoor unit b Piping between outdoor units NOTICE There are restrictions on the refrigerant pipe connection order between outdoor units during installation in case of a multiple outdoor unit...

Page 11: ...it MUST be handled in a different manner Install a water filter at the water inlet in order to prevent foreign materials such as dust sand from entering the plate heat exchanger Scale can stick to the...

Page 12: ...ow rate D Model D RWEYQ8 12 120 l min RWEYQ14 190 l min 3 Hydronic flow rate E The value E is the design flow rate calculated by the hydronic engineer when designing the building system Correct valve...

Page 13: ...ic component box cover Excessive force can deform the cover resulting in entering of water to cause equipment failure 4 SW8 2 1 5 2 Mounting the outdoor unit 5 2 1 To provide the installation structur...

Page 14: ...m of straight section can be ensured 120 mm 500 mm 5 3 4 To connect the refrigerant branching kit For installation of the refrigerant branching kit refer to the installation manual delivered with the...

Page 15: ...umstances Use the following procedure to remove the pinched piping 1 Remove the valve cover and make sure that the stop valves are fully closed a c d b a Service port and service port cover b Stop val...

Page 16: ...nt in the refrigerant piping for example water may have entered the piping first carry out the vacuum drying procedure below until all moisture has been removed All piping inside the unit has been fac...

Page 17: ...k the vacuum by pressurising with nitrogen gas to a gauge pressure of 0 05 MPa 0 5 bar and repeat steps 1 to 3 until all moisture has been removed 4 Depending on whether you want to immediately charge...

Page 18: ...CR 100 charge an additional 0 5 kg of refrigerant per outdoor unit In case of heat recovery mode Formula R X1 22 2 0 37 X2 19 1 0 26 X3 15 9 0 18 X4 12 7 0 12 X5 9 5 0 059 X6 6 4 0 022 1 04 A C R Addi...

Page 19: ...t the refrigerant tanks to each outdoor unit NOTICE The refrigerant charging port is connected to the piping inside the unit The unit s internal piping is already factory charged with refrigerant so b...

Page 20: ...he water circulation system otherwise the plate heat exchanger will freeze 4 Check if the water flow rate is correct otherwise the plate heat exchanger will freeze Measure any water pressure loss befo...

Page 21: ...oor unit PCB A1P b Unit A master outdoor unit c Unit B slave outdoor unit d Unit C slave outdoor unit e Outdoor unit other system transmission F1 F2 f Outdoor outdoor unit transmission Q1 Q2 g Indoor...

Page 22: ...f the 2 10 V DC output signal is 50 mW Exceeding this power can result in damage of the system Always use shielded cables with a minimal cross section of 0 75 mm and a length limited to 100 m The cont...

Page 23: ...refrigerant charge test run etc and making field settings demand operation low noise etc happens by way of operating the push buttons See also 6 1 2 Field setting components on page 23 6 1 3 To access...

Page 24: ...shed and normal the 7 segment display indication state will be as below default situation when shipped from factory Stage Display When turning on the power supply flashing as indicated First checks on...

Page 25: ...ws 1 5 The current Te target parameter position 1 6 The current Tc target parameter position 1 13 Shows the total number of connected outdoor units in case of multiple outdoor system 1 17 1 18 1 19 Sh...

Page 26: ...operation not only the outdoor unit but the connected indoor unit will operate as well Working on an indoor unit while performing a test operation is dangerous NOTICE Be sure to turn on the power 6 ho...

Page 27: ...lves opening Judgement of piping length In case Hydrobox units are present in the system the pipe length check and the refrigerant situation check will not be performed Make sure to carry out the syst...

Page 28: ...oor units 8 Troubleshooting 8 1 Solving problems based on error codes In case of a displayed malfunction code perform correcting actions as explained in the malfunction code table After correcting the...

Page 29: ...L 4D108945A A Charge port B Stop valve with service port 7 9 mm flare connection C Cooling water inlet D Cooling water outlet Charge port Service port Filter Check valve Pressure relief valve Solenoid...

Page 30: ...reless user interface m Water system connection Heat pump system g c g g h g g c c c d f e i j b a a Unit b Refrigerant piping c VRV DX indoor unit d LT Hydrobox unit e BP box required to connect Resi...

Page 31: ...over time restricting the energy transfer to the outdoor unit s coil Heating capability decreases and the system needs to go into defrost operation to be able to deliver enough heat to the indoor unit...

Page 32: ...s the air flow direction adjust button only for double flow multi flow corner ceiling suspended and wall mounted Refer to 12 4 Adjusting the air flow direction on page 32 for details To stop 5 Press t...

Page 33: ...nd in order to ensure the best possible maintenance of your units we recommend to enter into a maintenance and inspection contract on top of normal maintenance activities Our network of dealers has ac...

Page 34: ...r centralized control it shows that this is a slave user interface When the cool heat changeover remote control switch is installed and the display shows change over under centralized control this is...

Page 35: ...minutes 14 2 17 Symptom The inside of an outdoor unit is warm even when the unit has stopped This is because the crankcase heater is warming the compressor so that the compressor can start smoothly 14...

Page 36: ...4P452190 1A 2017 04 Copyright 2017 Daikin 4P452190 1 A 0000000Y...

Reviews: