Integra Feed-Link
4. Load Cell Installation
Installing the Load Cell Base
1. Shortening the anchor bolt may be required.
It can protrude no more than 1-1/4" above
the foundation.
NOTE: You
may find it easier to put the nut on the bolt
and cut the bolt flush with the nut. This way
the threads are not stripped on the bolt, and
there is not a problem getting the nut on.
2. Position load cell base under bin leg and
around anchor bolt as shown.
3. Replace washer and nut onto anchor bolt.
DO NOT tighten fully until assembly is
complete.
Figure 4F Cut anchor bolt so it sticks up less than
1-1/4" from foundation.
Figure 4G Slide Cell Base Under Leg
Figure 4H Leave anchor bolt loose until assembly
is complete.
Anchor bolt
Reciprocating saw
Bin leg
Load cell base
Load cell base