![Cumberland INT-4807 Installation And Operation Manual Download Page 11](http://html1.mh-extra.com/html/cumberland/int-4807/int-4807_installation-and-operation-manual_2697971011.webp)
4. Load Cell Installation
PNEG-1323
Integra Feed-Link
11
Raising the Bin
1. Place 4 x 4 spanner board under bin hopper
braces.
2. Center lift jack under 4 x 4 spanner brace.
3. Lift bin with jack about 4". This should lift two
(2) bin legs.
4. Remove leg anchor base plate.
Figure 4D Jacking Up the Bin
Figure 4E Lift Bin about 4"
Only install load cells on an
empty bin. Lifting a bin with
feed in it can result in damage
to the bin and potential
personal injury.
4 x 4 Spanner board
Jack
Lifted bin leg
Anchor base plate