Step 19 — Prepare Swing Beam Attachments:
Depending on the swing frame option to be installed, different preparations must be made before proceeding.
9 Foot Swing Beam:
For a
9 ft. Beam fastened perpendicular to the roof
, drill
two 7/16" diameter holes as shown above left. Insert 3/8"
Weld Nuts from the beam hardware bag before moving to
the step 20.
For a
7 ft. Beam fastened perpendicular to the roof
,
The top hole should be 3/8" diameter, the bottom two 7/16"
diameter. Insert a 5/16" Weld Nut into the top hole and
3/8" Weld Nuts from the beam hardware bag in the bottom
holes before moving to the step 20.
4-1/8"
4-1/8"
4-1/8"
4-1/8"
Align to top hole
8"
8"
8"
8"
4"
9 ft. Beam Parallel to Roof
7 ft. Beam Parallel to Roof
9 ft. Beam Perpendicular to Roof
7 ft. Beam Perpendicular to Roof
For a
9 ft. Beam fastened parallel to the roof
, drill three
holes as shown above right. The top hole should be 3/8"
diameter, the bottom two 7/16" diameter. Insert a 5/16"
Weld Nut into the top hole and 3/8" Weld Nuts from the
beam hardware bag in the bottom holes before moving to
the step 20.
For a
7 ft. Beam fastened parallel to the roof
, drill three
holes as shown above right. The top hole should be 3/8"
diameter, the bottom two 7/16" diameter. Insert a 5/16"
Weld Nut into the top hole and 3/8" Weld Nuts from the
beam hardware bag in the bottom holes before moving to
the step 20.
7 Foot Swing Beam:
27-1/2" to top of post