5.
Select the next adjacent wall panel, going in a clockwise direction around the perimeter
and follow the same steps as above: Align, lock to the floor, lock to the adjacent wall
panel and double check for alignment making sure panel is flush on all sides and on top
with the adjacent panels and floor.
6.
Repeat this procedure with each wall panel working your way around the perimeter of
the cooler in a clockwise fashion.
7.
When installing the Door panel, DO NOT REMOVE THE DOOR FROM DOOR FRAME.
Follow the same recommendations as when installing the wall panels.
Door frame panel
must be LEVEL and PLUMB
. Ensure it is flush at the top with all adjacent panels. DO NOT
screw-in the door threshold yet.