background image

 

Section 1 

Introduction and Safety 

 

An Introduction to Dielectric Withstand Testing with the HT-S 

 
The continuity test/dielectric withstand test is a production line test which is recognized by safety 

agencies worldwide as a valid criterion of safe assembly of end-use equipment.  The test ensures that the 
primary circuit power and ground conductors were properly wired and connected for safe operation.  It also 
applies a high-voltage potential between power and ground conductors to make sure that no unintentional 
leakage or arcing paths exist between power and ground.  The test consists of a ground continuity check, a 
leakage current check and a high voltage check.  It is non-destructive to the equipment under test, and can 
be accomplished in a short time. 

 
The  purpose  of  dielectric  testing:    Dielectric  testing  is  a  simple,  non-destructive  method  of 

verifying  the  adequacy  of  electrical  insulation  to  withstand  the  sort  of  transients  that  can  occur  during 
transient  (surge)  events.    In  addition,  the  dielectric  test  can  verify  that  the  insulation  in  question  has  an 
adequate amount of performance "headroom".  This is necessary to ensure that the insulation does not fail 
because of degradation of the insulation due to aging, moisture, wear due to vibration, etc. 

 
The  method  of  dielectric  testing:    A  high  voltage  (typically  1000  Volts  or  higher)  is  applied 

between  two  conductors  that  are  "supposed"  to  be  electrically  insulated  from  each  other.    If  the  two 
conductors (an insulated "live" wire, and a metal enclosure, for example) are completely isolated from each 
other, then the application of a large voltage difference between the two conductors will not allow current 
to flow between the conductors.  The insulation will "withstand" the application of a large voltage potential 
between the two conductors - hence the term "dielectric withstand test".   In general, there are two results of 
the test that are considered a failure of the insulation:  (1) excessive current flow during the test due to low 
insulation  resistance  of  the  insulating  material  which  separates  the  two  conductors,  and  (2)  an  abrupt 
dielectric breakdown due to electrical arcing or discharge, either through the insulation material, over the 
surface of the insulation material, or a discharge through air. 

 
The determination of a suitable test voltage:  If the test voltage is too low, the insulation material 

in question will not be adequately stressed during the test.  This could cause inadequate insulation to pass 
the test, and be considered acceptable.  On the other hand, if the test voltage is too high, then the test could 
cause permanent damage to an insulation material that is otherwise adequate for the application.  A general 
"rule  of  thumb"  that  is  used  for  the  testing  of  mains  wiring  which  operates  at  voltages  of  120-240Vac  is 
1000V plus two times the operating voltage.  Using this rule, 120V wiring would be tested using a voltage 
of 1240Vac. 

 
Duration of the test:  Generally, the test voltage is applied for one minute, in order to adequately 

stress the insulation.  Many standards allow the test duration to be reduced to 1 second for production-line 
testing in order to accommodate large-volume production testing.  In this case, standards quite often require 
that the test voltage be increased by 20% in order to ensure that the shorter test duration of one second will 
adequately test the insulation in question. 

 

Safety Precautions 

 
The dielectric withstand test generates voltages of up to 2000 Volts AC (HT-2000S & HT-3000S),  

up to 3000 Volts AC(HT-4200S), up to 2800 Volts DC (HT-2800S & HT-3000S) or up to 4200 Volts DC 
AC (HT-4200S) at potentially lethal current levels.  Currents of as little as 5 mA at 120V can cause death, 
and the HT-S is capable of generating 20mA  AC at up to 2000 Volts (10mA at up to 3000Volts for HT-
4200S), and 5mA DC at up to 2800 Volts (up to 4200 Volts for HT-4200S).  The HT-S has been designed 
to  minimize  exposure  to  high  voltages.    However,  the  potential  for  serious  injury  or  death  exists  and 
personnel should be aware when they conduct this test. 

Any use of this equipment other than as specified in this manual may result in a safety hazard. 
 

Summary of Contents for HT-2000S

Page 1: ...HT S Series Dielectric Withstand Tester With Ground Continuity Check Instruction Manual for Models HT 2000S 0 2000VAC HT 2800S 0 2800VDC HT 3000S 0 2000VAC 0 2800VDC HT 4200S 0 3000VAC 0 4200VDC...

Page 2: ...2...

Page 3: ...g logic controlled circuit design and ergonomic front panel and represents the latest in high voltage production line testing To fully appreciate all the features of your new meter we suggest that you...

Page 4: ...Interface PN 00 RI 19 Interlock PN 00 XI 19 Section 3 20 Operating Instructions 20 Setting up your Tester 20 AC Line Voltage Requirements 20 Fuse Replacement 21 Initial Checkout Procedure 21 High Volt...

Page 5: ...5 Technical Assistance 30 Contact Information 30 Section 5 31 Maintenance and Calibration 31 Service Information 31 Cleaning 31 Calibration Information 31...

Page 6: ...ring the test due to low insulation resistance of the insulating material which separates the two conductors and 2 an abrupt dielectric breakdown due to electrical arcing or discharge either through t...

Page 7: ...that a low resistance ground is provided by the building wiring If the HT S is used on a high resistance grounding circuit dangerous high voltages may be present to the operator In addition the power...

Page 8: ...with his right hand This will allow the greatest separation between the operator and the test being conducted The HT S is designed to bleed the high voltage away after the test has concluded In order...

Page 9: ...emoving the Test Return Lead clip from the equipment under test and reconnecting it taking care to make a good connection The unit should then be retested If a failing result is repeated the connectio...

Page 10: ...leakage current is below the limit set by the rear panel adjustment Sporadic Leakage Current Failures If the red Excess Leakage LED light is on the buzzer sounds and the test is terminated the leakage...

Page 11: ...n a problem has been found with the insulation between primary and ground The equipment under test should be examined reworked and successfully tested before being shipped High Voltage Discharge The H...

Page 12: ...buzzer sounds and any voltage stored in the equipment being tested is bled off by a resistor bank in the HT S unit The voltage discharge progress is shown by the front panel meter Failure modes are s...

Page 13: ...ge Limit Voltage Adjust Ground Continuity Defeat Switch Ground Continuity Limit Ground Continuity Offset Tamper proof operation available by removing adjustment shafts ENVIRONMENTAL Operating Temperat...

Page 14: ...utes to become familiar with the use of its controls indicators and connectors The front panel features of the HT S are shown in Figure 1 and Figure 2 then described in Table 2 Figure 1 Front Panel Co...

Page 15: ...15 Figure 2 Front Panel Controls Indicators and Connectors for HT 4200S...

Page 16: ...ground circuit resistance is acceptable the green continuity LED will light and the test will continue If the Ground Check switch is defeated by the operator both LED s will be lit for the duration of...

Page 17: ...T S tester take a few minutes to become familiar with the use of its controls indicators and connectors The rear panel features of the HT S are shown in Figure 3 and described in Table 3 Figure 3 Rear...

Page 18: ...passed for testing of double insulated equipment and other types of equipment without a grounding pin in the line cord 9 Ground Resistance Setting Adjustment Used to adjust the Ground Continuity pass...

Page 19: ...Output Full Voltage 7 Output Excess Leakage 8 Output Hipot Pass 9 Output Hipot Fail 10 Output Any Failure 11 Output COM2 12 Common Table 4 Relay Interface Pin Configuration Interlock PN 00 XI The Saf...

Page 20: ...essories which meet the manufacturer s specifications shall be used Connect this equipment to grounded outlet only The integrity of the test system grounding is dependent on building ground If reshipm...

Page 21: ...s AC and 2800 Volts DC or up to 3000 Volts AC and 4200 Volts DC for HT 4200S generated by the HT S is exposed during this test A risk of shock exists Exercise care when using the HT S High Voltage Per...

Page 22: ...e High Voltage Device socket may be as much as 2000 volts AC or 2800 volts DC or up to 3000 Volts AC and 4200 Volts DC for HT 4200S Proceed with caution 1 Disconnect all leads of the HT S front panel...

Page 23: ...200S HT 3000S HT 2000S Voltage Type AC Leakage Current Level 5 mA High Voltage Ramp Time 1 second High Voltage Level 1200 Volts High Voltage Test Time 2 seconds Ground Continuity Level 1 50 HT 2800S V...

Page 24: ...of supply and turn the power switch to the I or ON position Push the RESET button The yellow TEST indicator should light indicating that the HT S is ready to test e Use the AC DC button to select the...

Page 25: ...reached The test can be terminated at any time by pressing the RESET button 6 Check the position of the Ground Check switch before testing Setting the Ground Check Switch This switch controls whether...

Page 26: ...t in shortcut circuit the green alligator clip end to the Ground Connector Tip connected on step 3 See Figure 6 5 For HT 4200S plug the supplied 18 AWG GL Test Lead Alligator Clip Banana Plug ends bla...

Page 27: ...sistance measurement is more than 1 50 the display will show OPEn Operation Techniques The following paragraphs describe how to operate the HT S tester Before proceeding with testing the HT S tester s...

Page 28: ...t set on the HT S unit the green Ground OK LED will light and the test will continue 5 2 Ramp the voltage at the rate set by the Ramp Time procedure o If leakage current between the AC pins of the pow...

Page 29: ...y cord and the chassis ground of the unit rises above the value set by the Leakage Limit procedure the red Excess Leakage LED will light the buzzer will sound and the test will terminate o If the leak...

Page 30: ...m Compliance West USA is available Phone 800 748 6224 Hours 8 30 AM 4 30 PM Pacific Time Also available on our web site at www compwest com Contact Compliance West USA 650 Gateway Center Way Suite D S...

Page 31: ...tion and or repair of instruments that are beyond their warranty period Contact the manufacturer for a cost quotation Ship the instrument and your remittance according to the instructions given by the...

Reviews: