M02S40N16-00
WSA-XEE
122-402
39
8 Maintenance
8.1 General
description
Maintenance must be done by authorized centres or by qualified personnel.
The maintenance allows to:
•
maintain the unit efficiency
•
increase the life span of the equipment
•
assemble information and data to understand the state of the unit efficiency and avoid possible damages
Before checking, please verify the following:
•
the electrical power supply line should be isolated at the beginning
•
the unit isolator is open, locked and equipped with the suitable warning
•
make sure no tension is present
After turning off the power, wait at least 5 minutes before accessing to the electrical panel or any other electrical component.
Before accessing check with a multimeter that there are no residual stresses.
8.2 Inspections
frequency
Perform an inspection every 6 months minimum.
The frequency, however, depends on the use.
In the event of frequent use it is recommended to plan inspections at shorter intervals:
•
frequent use (continuous or very intermittent use, near the operating limits, etc)
•
critical use (service necessary)
√
intervention frequency (months)
1
6
12
1
presence corrosion
X
2
panel fixing
X
3
fan fixing
X
4
coil cleaning
X
5
water filter cleaning
X
6
check the exchanger efficiency
X
7
circulating pumps
X
8
check of the fixing and the insulation of the power lead
X
9
check of the earthing cable
X
10
electric panel cleaning
X
11
capacity contactor status
X
12
termina closing, cable insulation integrity
X
13
voltage and phase unbalancing (no load and on-load)
X
14
absorptions of the single electrical loads
X
15
test of the compressor crankcase heaters
X
16
leak control*
X
17
survey of the refrigerant circuit operating parameters
X
18
protective device test: pressure switches, thermostats, flow switches etc..
X
19
Safety valves: refer to the local regulations
20
control system test: setpoint, climatic compensations, capacity stepping, water / air flow-rate variations
X
21
control device test: alarm signalling, thermometers, probes, pressure gauges etc..
X
* European regulation 303/2008
Refer to the local regulations; and ensure correct adherance. Companies and technicians that effect interventions of installation, maintenance/
repairs, leak control and recovery must be CERTIFIED as expected by the local regulations. The leak control must be effected with annual
renewal.
8.3 Unit
booklet
It’s advisable to create a unit booklet to take notes of the unit interventions.
In this way it will be easier to adequately note the various interventions and aid any troubleshooting.
Report on the booklet:
•
date
•
type of intervention effected
•
intervention description
•
carried out measures etc.
Summary of Contents for WSA-XEE 182
Page 8: ...8 WSA XEE 122 402 M02S40N16 00 2 4 Removable fan section for shipping...
Page 15: ...M02S40N16 00 WSA XEE 122 402 15 5 6 Connections performer by customer Q 6...
Page 58: ...58 WSA XEE 122 402 M02S40N16 00 Page intentionally left blank...
Page 59: ...M02S40N16 00 WSA XEE 122 402 59 Page intentionally left blank...