Chapter 3 — Flue and Combustion Air Venting
Part No. 750-295
3-11
Engineered Design
-
When determining boiler room air requirements for an unconfined space the
“Engineered Design” method may be used. Following this method, consideration must be given to the size of
the room, airflow and velocity of air as follows:
A. Two permanent air supply openings in the outer walls of the boiler room are recommended. Locate one at
each end of the boiler room, preferably below a height of 7 feet. This allows air to sweep the length of the
boiler (see
Figure 3-9
).
Figure 3-9 Engineered method
B. Air supply openings can be louvered for weather protection, but they should not be covered with fine mesh
wire, as this type of covering has poor air flow qualities and is subject to clogging with dirt and dust.
C. A vent fan in the boiler room is not recommended as it could create a slight vacuum under certain
conditions and cause variations in the quantity of combustion air. This can result in unsafe burner
performance.
D. It is forbidden to have the total area of the air supply openings at less than one square foot.
E. Size the openings by using the formula (Area in ft
2
= cfm
a
/fpm
a
), where cfm
a
= cubic feet per minute of
air; fpm
a
= feet per minute of air.
F. Amount of air required (cfm):
1. Combustion Air = Maximum boiler horsepower (bhp) times 8 cfm.
2. Ventilation Air = Maximum boiler horsepower (bhp) times 2 cfm.
3. Total Air = 10 cfm per bhp (up to 1000 feet elevation, add 3% more per 1000 feet of added elevation).
G. Acceptable air velocity in the boiler room (fpm):
1. From floor to 7 feet high = 250 fpm.
2. Above 7 feet from boiler room floor = 500 fpm.
EXTERIOR WALL
FRESH AIR OPENING
EXTERIOR WALL
FRESH AIR OPENING
CLEARFIRE
®
BOILER
GAS
VENT
Summary of Contents for ClearFire CFH
Page 14: ...Chapter 1 Introduction 1 8 Part No 750 295 ...
Page 27: ...Chapter 2 Installation Part No 750 295 2 13 Figure 2 10 CFH wiring diagram typical 10 60 HP ...
Page 42: ...Chapter 3 Flue and Combustion Air Venting 3 14 Part No 750 295 ...
Page 90: ......
Page 92: ...Chapter 6 Model CFH Parts 6 2 Part No 750 295 6 1 CONTROL PANEL 10 60 HP ...
Page 93: ...Chapter 6 Model CFH Parts Part No 750 295 6 3 6 1 CONTROL PANEL 70 80 HP ...
Page 100: ...Chapter 6 Model CFH Parts 6 10 Part No 750 295 Standard gas train 30 HP ...
Page 105: ...Chapter 6 Model CFH Parts Part No 750 295 6 15 6 4 2 Gas Train Dual Fuel 30 HP dual fuel ...
Page 106: ...Chapter 6 Model CFH Parts 6 16 Part No 750 295 40 HP dual fuel ...
Page 107: ...Chapter 6 Model CFH Parts Part No 750 295 6 17 50 60 HP dual fuel ...
Page 110: ...Chapter 6 Model CFH Parts 6 20 Part No 750 295 40 HP dual fuel lgp ...
Page 111: ...Chapter 6 Model CFH Parts Part No 750 295 6 21 50 60 HP dual fuel lgp ...
Page 112: ...Chapter 6 Model CFH Parts 6 22 Part No 750 295 6 4 4 Gas Train Propane 30 HP propane ...
Page 113: ...Chapter 6 Model CFH Parts Part No 750 295 6 23 40 HP propane ...
Page 114: ...Chapter 6 Model CFH Parts 6 24 Part No 750 295 50 60 HP propane ...
Page 120: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com ...