19
YOURx-Aerial Terminal
__________________________________________________________
Installation Manual
Direct: 763.476.6866 • National: 800.422.2537 • www.SeeClearfield.com • [email protected]
Manual 019588 REV B - Sept 2018
Ribbon
Step 1:
Bring the ribbon fibers you wish to splice to the splice tray in your workspace.
Note:
Provided with the splice tray are 3 ribbon tie-downs which utilize a split grommet and u-channel (plastic retention
cover) which will allow the ribbon to be secured into the tray even in mid-span/ring cut applications.
Step 2:
3ft from the end, slip the split rubber grommet onto the ribbon, followed by the u-channel over the opposite side.
Note:
Extra ribbon tie-downs are available in a kit, which can be ordered seperately (P/N 019501).
Step 3:
After protecting the ribbon fiber with the ribbon tie-
down, secure it into the tray using small cable ties.
Note:
The splice tray features tie-down holes on each side
of the tray, which will allow for 5 ribbon tie-downs per side, in
addition to one ribbon tie down on each side in the assembly
fiber location.
Assembly Fiber
Location
Incoming
Fiber
Tie-Down
Step 4:
Remove the 5 meter ribbon fiber assembly that is
wrapped around the center spools below the splice tray area
and taped to the top. 24 fiber configurations will arrive with
two 12 fiber ribbons.
Step 5:
Bring the fiber assembly to the splice tray in your
workplace and secure it into the splice tray in the same
manner as you did for your incoming ribbon fiber.
Note: Clearfield recommends leaving 3ft/1m after the ribbon
tie down for use in splicing in the splice tray.