Filling with water:
•
Fully open the high point air traps and valves.
•
Fill the system with water.
•
Run the pumps.
•
Check the circuit for leaks (pressure gauges).
•
Drain the water through the system’s lowest point in order to remove dirt, scale, and other impurities from the pipes and which could clog the coil.
•
If the water has been treated, test its pH. We recommend injecting an If it had been treated, check water condition (pH). We recommend adding a scale and corrosion inhibitor
to the system.
•
Refill the system with water then turn off the pumps and completely purge the system of air.
•
Seal any leaks found on the couplings.
Check of the fluids
•
Check the pressures and temperatures of the fluids, the adjustment of the control instruments and the balancing of the circuits.
6. EVAPORATIVE HUMIDIFIER (HR)
Clean the tank to remove dust created during assembly.
•
Check the pump’s direction of rotation.
•
Adjust the water level in the tank. It should be 1 cm below the overflow.
Adjusting the
blowdown water
flow rate
Start-up carried out without a
water analysis or water softening
system.
For reasons of safety, the flow
rate of the blowdown water must be
equal to that of the evaporated
water (see table below) after one
month’s operation. Follow the
blowdown purge instructions below
to reduce excessive water
consumption.
EVAPORATION AT NOMINAL FLOW (l/h) FOR AN INLET TEMPERATURE OF 30°C at 40% RH.
Use the table above to determine whether a water softening system is necessary.
If a water softener is not used, the blowdown water flow rate must be adjusted based on the water quality after one month’s operation.
Check the flow rate of the blowdown water each time work is carried out on the water supply system, the water softener, or the humidifier.
MAST’AIR
Nominal Q in m3/h
Humidification efficiency
60%
80%
90%
Square size
800
60000
174
233
251
1000
77000
223
298
322
1200
94000
272
364
393
1400
110000
318
426
460
1600
130000
375
503
544
Low profile size
C600
45000
101
177
190
C750
56250
163
218
235
C900
67500
195
262
282
C1050
78750
228
306
329
C1200
90000
261
349
376
Pump connection
Water level
Floater valve assembly
Mains water
supply
Overflow
drain
Drain plug
Rotation
Check
Tap
(Dec. regulation)
Tap (cell supply