Installing the VVT Zone II
VVT Zone II Controller
CARRIER CORPORATION ©2019
Installation and Start-up Guide
All rights reserved
14
Wiring specifications
Cable from sensor to controller:
If <100 ft (30.5 meters) 22 AWG, unshielded
If >100 ft (30.5 meters) 22 AWG, shielded
Maximum length:
500 feet (152 meters)
To wire ZS sensors to the controller
ZS Sensors are thermistor-based temperature sensors that may optionally sense humidity, CO
2
, or VOC. ZS
Sensors are wired to the Rnet port on i-Vu® Open controllers.
You can use the following ZS sensors:
•
ZS Standard
•
ZS Plus
•
ZS Pro
NOTE
The ZS CO2 model uses 190 mA during sample period. Use auxiliary 12 Vdc, unless it is the only device on
the Rnet port.
1
Remove power from the VVT Zone II.
2
Partially cut, then bend and pull off the outer jacket of the Rnet cable(s). Do not nick the inner insulation.
Strip about .25 inch (.6 cm) of the inner insulation from each wire.
Outer Jacket
Inner insulation
.25 in.
(.6 cm)
3
Wire each terminal on the sensor to the same terminal on the controller. See diagram below.
NOTE
Carrier recommends that you use the following Rnet wiring scheme:
Connect this wire...
To this terminal...
Red
Black
White
Green
+12V
Rnet-
Rnet+
Gnd
4
Apply power to the VVT Zone II.