CONTROL CONFIGURATION
An Equipment Touch, Equipment Touch App, or Field Assistant will be required for control configuration.
The unit control configuration must be completed by installing contractor or start-up contractor prior to equipment
start-up. If completed by the installing contractor, provide to the Carrier startup team.
PROJECT INFORMATION
Project Name______________________________________
Address _________________________________________
City______________________________________________
State/Providence_______________ Zip Code ____________
Installer __________________________________________
Contact Name_____________________________________
Contact Phone_____________________________________
Contact Email______________________________________
UNIT INFORMATION
Model Number_____________________________________
Serial Number _____________________________________
INSTRUCTIONS
Check the box to verify the activity has been completed. If the activity does not apply, write N/A in the box. The admin
password (1111) will be required for control configuration.
Record the control and setpoint configurations on the included tables
UNIT SETUP
Equipment Configuration
(
Home
Setup
Misc Settings
Config
)
Verify that the SF Option matches the supply fan operating mode from the pre-startup checklist
Verify that the EF Option matches the exhaust fan operating mode from the pre-startup checklist
Verify that the HGRH Option matches the unit model number
Configure the Dehum Option to match the dehum enabled by condition from the pre-startup checklist
Verify the Heating Option matches the unit model number or configure to match the field provided heat from the
pre-startup checklist
Configure the Cooling Enabled By to match the cooling enabled by condition from the pre-startup checklist
Configure the Heating Enabled By to match the heating enabled by condition from the pre-startup checklist
Verify the Temp Option #1 configuration matches the unit configuration (OAT, SAT for units without ECW, ECAT,
OAT, SAT for units with ECW)
Verify the Temp Option #2 configuration matches the unit configuration (None for units without ECW, RAT, WExAT
for units with ECW)
Verify the Humidity Option #1 configuration matches the unit configuration (OARH, SARH for units without ECW,
ECRH, SARH for units with ECW)
Verify the Humidity Option #2 configuration matches the unit configuration (None for units without ECW, RAT,
WExAT for units with ECW)
Verify the Air Pressure Options configuration matches the unit configuration (None for units without pressure
control option, SF-DPT for units with pressure control option and supply fan only, SF-DPT and ZN-DPT for units with
pressure control option and supply and exhaust fan). ZN-DPT for supply fan only pressure control available as ETO
for field enabled.
Tech Settings
(
Home
Setup
Tech. Setup.
)
Configure the Occupancy Control to match the occupancy control from the pre-startup checklist
Verify Manual Occ Control is set to “OFF” (unless needed for temporary operation)
Verify Enable Unit Operation is set to “OFF” (until equipment start up has been completed)
Verify Emergency Shutdown is set to “OFF”
Verify Emergency Heat Enable is set to “OFF”
Set the SF Minimum Setting to 50% (unless value has been set by air balance contractor)
Configure ZAT/SAT Reset (if required) based on the pre-startup checklist
Configure HW Valve Minimum % (if required) based on the pre-startup checklist
Configure SF Occ/Unocc based on unoccupied supply fan operation on the pre-startup checklist