TECHNICAL PASSPORT. INSTALLATION and OPERATION MANUAL
TECHNICAL PASSPORT. INSTALLATION and OPERATION MANUAL
18
9.2 Combustion adjustment
Bottom chamber door as well as all
inspection openings must be closed and
sealed. Inside the boiler there should
not be any fire or smoke. Press
F4
key to
start calibration of lambda sensor. Over
a period of 2-3 min. the lambda sensor
is calibrated and can shift on to ignition
of the boiler. This calibration is only
necessary before igniting the boiler. Once
the boiler has entered work mode no
calibration is required between reloads.
To start ignition of the boiler press
F1
key
and load the boiler with the initial dose
of twigs and small wood, then kindle
them. It is necessary to make a good glow
bed in order that firewood loaded in the
combustion chamber subsequently makes
a good fire. During the glow-making
period it is necessary to hold the upper
door slightly open to allow exhaust gases
be suctioned through the slit in its top
part. Once you have the glow bed ready,
top up with firewood to fill the entire
volume of the combustion chamber.
The suction fan in the rear provides for the
maintenance of combustion process in the
boiler. The inflow of fresh air to the boiler
is made possible by 2 flaps operated by
motor actuators. An important condition
is that flaps be well centered before the
actuator is fastened to the respective flap.
Sustainable combustion process depends
on the proper adjustment of the flaps and
the correct settings of the controller.
9.3. Requirements concerning cleaning
and maintenance of the boiler.
*
Caution!
Hot surfaces.
Before cleaning the boiler
,
make
sure the fire in it has died out and
the boiler has cooled down
.
9.3.1. Cleaning and maintenance by
customer.
- Exploitation of the boiler and the type
of used fuel determine how often have
to clean the boiler residues from the
combustion process.
- We recommend cleaning the ashes from
the upper chamber of the boiler to be
done
every
3 - 4
days
. In the case where
ashes has reached faster the level of
primary air openings, then ashes must
be cleaned immediately (see diagram
10). Do not let the ashes clog these
holes.
- The ash accumulates in lower chamber
as well. Clean ash when its level
reaches
1/3
of lower chamber volume (Diagram
13). Uncleaned ash aff ects boiler
operation.
Diagram 12
9.3.2. Cleaning and maintenance by
authorized installer / service
Boiler cleaning and maintenance must be
performed by a technician / service shop
authorized for such operations. Before
the beginning of heating season must
be done inspection and maintenance of
following boiler parts:
1. Adjustment of boiler doors again.
Make sure the doors seal well. If
necessary, replace insulation rope at
the door with a new one. Make sure
that the new insulating rope is placed
correctly, following exactly the geometry
of channel. Pull the rope well to the door
corners by using a screwdriver.
Summary of Contents for Lambda series
Page 2: ......
Page 32: ...TECHNICAL PASSPORT INSTALLATION and OPERATION MANUAL TE 32...
Page 34: ......
Page 35: ......