Tekmar 265 Based Control System (or equal)
Sequence of Operation
The
Tekmar 265 Control (or equal) can control up to three (3) boilers and an Indirect W
ater Heater
. When a call for heat is received by the
Tekmar 265 Control, the control
will fire either one or more boilers in either parallel or sequential firing mode to establish a required reset water temperature in the system supply main based on outdoor temperature.
The boilers will modulate based on an
Analog communication signal established between the
Tekmar 265 Control and each boiler
’s Sage2.1™ Control.
The
boiler(s) and system supply water temperature will be reset together to maintain the input that is needed to the system. When a call for Indirect Hot W
ater is generated to the
Tekmar 265, the control will de-energize the zone pump control (ZC terminal), energize the Indirect pump and modulate the boiler firing to establish a setpoint temperature in the main for the Indirect Heater using Priority
.
The
Tekmar 265 also controls each boiler
’s pump and a post purge of leftover temperature in the boilers will occur at the end of the
call for Indirect Hot W
ater
.
X. Modular
installation (continued)
Figure
a
: Modular W
iring Diagram w/T
ekmar 265 Control
Summary of Contents for Alpine ALP080
Page 40: ...40 Figure 29 Condensate Trap and Drain Line V Condensate Disposal continued ...
Page 56: ...56 VIII Electrical continued ...
Page 57: ...57 VIII Electrical continued Figure 35 Wiring Connections Diagram ...
Page 58: ...58 Figure 36 Ladder Diagram VIII Electrical continued ...
Page 64: ...64 Figure 39 Modular Boiler Direct Vent Termination X Modular Installation continued ...
Page 65: ...65 Figure 40 Modular Boiler Concentric Vent Termination X Modular Installation continued ...