82
X. Modular installation (continued)
G
.
Modular Boiler Operating Information
(continued)
3.
Required Equipment and Setup
d. Modular Boiler Setup
Step
Description
Comments
1
Install and wire the Header
Sensor
Wire the header sensor to low voltage terminal strip terminals “Header sensor”.
nOTE
This step can not be skipped. The Sequence Master can not be “enabled”
unless a Header Sensor is installed.
2
Install Ethernet Cables between
boilers
Standard Ethernet type cables with RJ45 connectors are “plugged in” to the Boiler-to-Boiler
Communication Network connection located on the side of the boiler. When more than two boilers are
connected an RJ45 splitter may be used to connect the boilers. Refer to Figure 50.
3
Apply Power to All Boilers
4
Set Unique Boiler Addresses
Assign all boilers a
unique
Boiler Address using any number from 1 through 8.
WaRning
When two boiler’s addresses are the same undesirable simultaneous operation occurs.
5
Enable 1 Boiler Master
Enable only one
Sage2 Control’s Sequencer Master.
WaRning
When more than one Sequencer Master is enable erratic behavior will result.
6
Power Down All Boilers
7
Power Up Master Sequencer
“Enabled” Boiler First
8
Power Up Other Boilers
9
Confirm Communication
From the Home Screen of the Sage2 Control with the Master Sequencer “enabled”, select the Status
button. The Sequencer display shows the boiler address of the communicating boilers. Additionally,
from the “Home” screen select the “Detail” button and then the “Networked Boilers” buttons to view boiler
communication status.
If a boiler is not shown, check Ethernet cable connections and confirm all boilers have unique addresses.
Summary of Contents for Alpine ALP080
Page 40: ...40 Figure 29 Condensate Trap and Drain Line V Condensate Disposal continued ...
Page 56: ...56 VIII Electrical continued ...
Page 57: ...57 VIII Electrical continued Figure 35 Wiring Connections Diagram ...
Page 58: ...58 Figure 36 Ladder Diagram VIII Electrical continued ...
Page 64: ...64 Figure 39 Modular Boiler Direct Vent Termination X Modular Installation continued ...
Page 65: ...65 Figure 40 Modular Boiler Concentric Vent Termination X Modular Installation continued ...