Reliable Ground
A reliable ground must be maintained at all times. To ensure this, the rack itself
should be grounded. Particular attention should be given to power supply connections
other than the direct connections to the branch circuit (i.e. the use of power strips, etc.).
2.5
Installing the System into a Rack
This section provides information on installing the R423-E3 chassis into a rack unit with the
quick-release rails provided. There are a variety of rack units on the market, which may
mean the assembly procedure will differ slightly. You should also refer to the installation
instructions that came with the rack unit you are using.
Note
This rail will fit a rack between 26" and 33.5" deep.
2.5.1
Separating the Sections of the Rack Rails
The chassis package includes two rail assemblies in the rack mounting kit. Each assembly
consists of two sections: an inner fixed chassis rail that secures directly to the server
chassis and an outer fixed rack rail that secures directly to the rack itself (Figure 2-1).
Separating the Inner and Outer Rails
1.
Locate the rail assembly in the chassis packaging.
2.
Extend the rail assembly by pulling it outward.
3.
Press the quick-release tab.
4.
Separate the inner rail extension from the outer rail assembly.
Figure 2-1.
Separating the Rack Rails
Chapter 2. Server Installation
7
Summary of Contents for Bullx R423-E3
Page 1: ...bullx R423 E3 Installation and User s Guide extreme computing REFERENCE 86 A1 48FH 01...
Page 2: ......
Page 24: ...14 bullx R423 E3 Installation and User s Guide...
Page 28: ...18 bullx R423 E3 Installation and User s Guide...
Page 43: ...5 7 1 Serverboard Quick Reference Chapter 5 Advanced Serverboard Setup 33...
Page 44: ...34 bullx R423 E3 Installation and User s Guide...
Page 62: ...52 bullx R423 E3 Installation and User s Guide...
Page 92: ......
Page 94: ...84 bullx R423 E3 Installation and User s Guide...
Page 97: ......
Page 98: ...BULL CEDOC 357 AVENUE PATTON B P 20845 49008 ANGERS CEDEX 01 FRANCE REFERENCE 86 A1 48FH 01...