7
Boiler block assembly
Logano G615 - Subject to technical modifications
23
B
Remove boiler assembly tool.
Fig. 19 Inserting the tie rods
1
Tie rods (bottom)
2
Tie rods (top)
3
Tie rod with spring package
The next step describes the installation of the supply pipe
(
Æ
see Chapter 7.4, page 24).
7.3
Setting up the boiler block –
(assembled block)
B
Cut the straps.
B
Remove pallet.
Fig. 20 Boiler block on pallet
1
Securing straps
2
Pallet
B
Level the boiler block vertically and horizontally on the
base/foundation. Use the boiler section foot wedges
provided for this purpose.
B
After leveling the boiler block, remove the transport
safety brace from the top and bottom hub.
The following pages describe the installation of the supply
pipe and sensor well. You must do both irrespective of
whether the boiler is supplied pre-assembled or in
separate sections.
Fig. 21 Removing the transport safety brace
1
Top hub
2
Bottom hub
3
Transport safety brace
DANGER: Risk of fatal injury
from falling
objects.
B
Provide a suitable means of supporting
the load.
B
Observe all locally applicable
occupational health & safety regulations
regarding lifting equipment.
6 720 642 625-16.1o
1
2
3
6 720 642 625-17.1o
2
1
6 720 642 625-18.1o
3
1
2