11
System start-up
Logano G615 - Subject to technical modifications
45
11.5
Commissioning log
The Logano G615 can be used with an oil- or gas-fired
burner. Fill in the commissioning log for the appropriate
type of oil or gas burner carefully.
B
Sign all start-up work as completed and enter the
relevant date.
Commissioning operations
Individual steps
Comments (signature)
1.
Perform leak test of the entire system
2.
Fill the heating system with water
Æ
page 43
3.
Air purge the heating system
4.
Perform the leak test if the boiler was assembled on site
Æ
page 26
5.
Record the filling water quantity and composition in the
operator’s log (included with the technical
documentation).
6.
Check position of the flue gas baffles (do not install
baffles in the 16-section boiler))
Æ
page 29
7.
Check the fuel line for leaks.
8.
Start up the control panel
Æ
page 44
9.
Initial burner start-up
See burner
documentation
10.
Check the flue gas temperature
11.
Check vent pipe for leaks
12.
Check boiler and flue gas side for leaks
13.
Enter the fuel used in the table provided in the operating
instructions.
14.
Inform the owner and operator and hand over technical
documentation
15.
Confirm properly-completed commissioning
Company stamp/signature/date